**80th Avenue is closed from Cleveland Street north to Wilson Street. Detour is via 56th Avenue/Ravenna Road. Closure will be in place for several months.***
Work completed/in progress:
- Installed 1,450 of force main last week. Force main installation is approaching Taft St.
- Most culvert installation is complete between Cleveland St. and Taft St.
- 80th Avenue preliminary road building continues behind the force main construction.
- Partial milling of southbound lane of 80th Ave between Taft St and Wilson St.
Anticipated work activities for the coming week:
- Continue force main installation north of Taft St. and road building.