Progress Report:
This week included driveway and road crossing restoration on Hillsdale. Kentwood also worked on water service replacements on Lindburg and Chadwick.
Upcoming Work:
- Next week, any remaining water service work on Lindburg and Chadwick will be wrapped up and Kentwood will begin switching over the water services on Westwood to the temporary water main.
- Lawn restoration along Hillsdale is expected to be completed next week.
- Driveway and road restoration work on Lindburg and Chadwick will begin once water service work is complete.