May 27, 2026
Progress Report:
The project overall is nearing completion. Paving along Corporate Circle Drive & John F. Donnelly is complete and open to traffic. The old pump station has been demolished and abandoned. The existing force main pipe is currently being abandoned and will be completed by the end of this week. Pavement striping and traffic loops are installed. Final turf restoration and irrigation repairs will be wrapping up in the coming weeks.
On behalf of Holland Charter Township, we thank all those who were impacted by this utility construction project, in being patient and understanding during and after construction was complete.

