April 22, 2026
Progress:
K&R has now completed the gravity sewer installation for the project. Testing of the gravity sewer will be completed this week and upon completion, all active flow will be sent down the new sanitary gravity sewer to Pump Station No. 31.
Upcoming Work:
Restoration: Corporate Circle Drive & John F. Donnelly will be restored and paved in the coming month. Turf restoration and punch list items will continue to be worked on.
Pump Station No. 15 connection to the new force main is scheduled for MONDAY, APRIL 27. This connection will require the closure of 128th Avenue (Beeline Road to Riley Street) for a 1-day period.
Abandonment of the old force main will precede the pump station connection.