September 4, 2026
Here is a brief update on construction progress at the Wastewater Treatment Plant.
Work Completed:
- Control Structure D overflow pipes installed
- Control Structure C installed, along with gate valves and piping to Pond 3
- Bypass Control Structure installed, along with gate valves and piping to Ponds 3 and 4
- Control Structure B installed, along with most of the piping from the Bypass Control Structure
- Ponds 3 and 4 clay liner repaired
Upcoming Work:
- Complete installation of piping between Bypass Control Structure and Control Structure B
- Install piping from Pond 4 to Control Structure B
- Install piping from Pond 1 to Control Structure B
- Begin transfer of water from Pond 2 to Ponds 3 and 4