West Randall Lift Station

Important Information

West Randall Lift Station: Construct a second lift station adjacent to the existing West Randall Lift Station to accommodate proposed flows for the Southeast Regional Force Main.

Contact

Prein&Newhof
Will Thies, PE
(616) 364-8491
wthies@preinnewhof.com

Contractor
Grand River Construction
(616) 669-5611

Muskegon County
(231) 724-3440

Work completed/in progress:

  • Grand River is pouring the first set of wet well infill concrete today.
  • They are also working on formwork and conduit installation for the dry well intermediate platform.

Anticipated work activities for the coming week:

  • Reinforcing steel, floor sleeves and drains, and conduits will be installed in the intermediate platform slab, which will be poured as soon as next week.

Work completed/in progress:

  • Grand River stripped forms from the lift station walls and began tying steel for the concrete wet well fillets.

Anticipated work activities for the coming week:

  • The first set of wet well fillets will be poured.
  • Grand River will begin forming and installing conduit for the intermediate dry well platform.

Work completed/in progress:

  • The final wall section was poured this week. The base slab and walls are now complete.
  • Grand River is stripping forms from the previous wall section today.

Anticipated work activities for the coming week:

  • Grand River will continue removing formwork and preparing for installation of the wall pipes and leak testing of the structure.

Work completed/in progress: Conduit and steel installation continued this week.

Anticipated work activities for the coming week: Grand River will install the remaining formwork and intends to pour the final wall on December 27.

Work completed/in progress: the third wall section was poured on Tuesday.

Anticipated work activities for the coming week: Grand River will continue to prepare for the fourth and final wall pour, which is tentatively scheduled for December 23.

Work completed/in progress:
  • Second wall pour completed and third wall pour preparations underway.
Anticipated work activities for the coming week:
  • The third wall pour is scheduled for Tuesday.

Work completed/in progress:

  • Preparations for the second wall pour were delayed due to weather. The wall forms and bulkheads have been installed.

Anticipated work activities for the coming week:

  • The second wall pour is now scheduled for Monday.

Work completed/in progress:

  • The first wall pour was completed this week (see photos).
  • Conduit and rebar are installed for the second wall pour.

Anticipated work activities for the coming week:

  • Forms will be stripped and moved to the next wall section. The second wall pour is scheduled for next week Wednesday.

Work completed/in progress:

  • Installation of the remaining wall forms was delayed due to rain and high winds this week.
  • All wall pipes and conduit are now in place and the wall is nearly ready for concrete.

Anticipated work activities for the coming week:

  • The date of the first wall pour is scheduled for next week Wednesday.
  • GRC is moving forward with preparing for the second wall pour in the southeast corner of the structure.

Work completed/in progress:

  • Installation of reinforcing steel and conduit for the first wall pour is nearly complete.

Anticipated work activities for the coming week:

  • Grand River Construction will install the remaining form work, with a pour planned for late next week.