Progress Report:
After milling the road and getting pipe/materials the week of July 6-10, Cutting Edge Excavating (contractor) was able to start in earnest and work their way east and south along Sand Hollow Drive. The contractor put in several storm laterals (sump lines) along with installing storm sewer around half way down Sand Hollow Drive between the driveways of 642 and 639 Sand Hollow Drive.
Upcoming Work:
The Contractor plans on continuing to install storm sewer and laterals down Sand Hollow Drive to the easement area between 611 Sand Hollow Drive and 608/590 Sleepy Hollow Lane and start installing storm sewer in the easement area. It is possible the Contractor is also able to get into Sleepy Hollow Lane.
Note:
Cutting Edge was able to use a water truck to brine the gravel on Wednesday. Cutting Edge is also working to repair sprinkling lines as they are damaged so please inform us if there is an issue with your sprinkling line after we have installed in front of your home.
To maintain traffic around the trench, it will be necessary at times to drive up into the grass to safely pass the jobsite. All disturbed areas of lawns will be regraded and reseeded as necessary.
Please also do not hesitate to reach out to Lucas Timmer (project manager), Jack Hoffman (project engineer) or Alden Baker (on site construction observer) with any questions that you may have as we will all be on site frequently. We appreciate everyone’s patience during construction.

