Progress Report:
Cutting Edge and S&S Sprinkling are continuing their work on completing restoration and sprinkling repairs throughout the neighborhood.
Cutting Edge hopes to be completed with restoration by October 15.
Roadwork: Removal of the road surface on Sleepy Hollow Lane, Tarry Town Road, and Sand Hollow Drive.
Storm Sewer: Excavation to replace existing corrugated plastic storm sewers and underdrain with new storm sewer.
Sump Lines: New sump discharge lateral piping will be installed to the right-of-way line. The contractor will reconnect your existing pipe. (Note: sump discharge lateral piping from the right-of-way line to the house is the responsibility of the homeowner).
Irrigation and Underground Dog Fence: Please mark your irrigation and underground dog fence in your yard with marker flags prior to construction. The Contractor will repair/replace damaged lines from construction but this would be much simpler if marked ahead of time.
Landscaping/Yards: Portions of yards will be damaged during construction to allow at minimum one lane of traffic through construction. Properties will be reseeded at the end of construction but property owners must participate in watering/maintaining new grass seed to ensure grass growth occurs.
Road Access: At least one lane of traffic will remain open throughout construction, though access may be limited at times. Asphalt paving will also limit access but a letter will be provided notifying property owners of when paving is anticipated to occur (weather dependent).
Driveways: You may temporarily lose driveway access when work is directly in front of your property, but you will not be left without access overnight.
Concrete Curing Time: If a portion of your driveway is replaced, access will be restricted longer while the concrete cures.
Mail: Temporary mailboxes will be set up on Mason Street. Amazon and other delivery drivers will continue having access for neighborhood deliveries.
Garbage Pickup: Standard waste service will continue. On pick-up days, please place your bins in an accessible location clear of construction.
P&N Engineer|
Lucas Timmer, Project Manager
616-394-0200
P&N Construction Observer
Jack Hoffman, Project Engineer
616-394-0200
Contractor
Cutting Edge Excavating
616-662-9653
Ottawa County Water Resources Commissioner
616-994-4530
Progress Report:
Cutting Edge and S&S Sprinkling are continuing their work on completing restoration and sprinkling repairs throughout the neighborhood.
Cutting Edge hopes to be completed with restoration by October 15.
Progress Report:
The project is entering into the final stages. Cutting Edge is now beginning the restoration process throughout the neighborhood, which includes the replacement of disturbed landscaping, damaged sprinklers, topsoil, and grass seed. Please see the attached letter from Cutting Edge giving details on their restoration plan: Sleepy Hollow Irrigation Topsoil Notice
Michigan Paving has informed us that the top layer of pavement will be paved this Friday, September 11, which is on schedule per my previous letter/update.
Similar to the first round of paving, please plan on having all vehicles off the road by 6:30 AM Friday morning. Please do not drive on the newly paved surface until at least 6:00 PM Friday evening. Vehicles may park at Niekerk Church as they have previously.
Reach out to me in the meantime with any questions. Thank you!
Paving Base Course:
Michigan Paving will be on site tomorrow (Tuesday, September 1) to pave the base course of your neighborhood. Please note the following regarding paving:
Irrigation:
Cutting Edge would like homeowners to test their sprinkler systems and note if they have any issues. Cutting Edge is already aware of many sprinkler lines that were damaged, but they want to make sure to identify and address any additional damage. If damage is noted, they will review it to determine whether it was caused by construction, and if so, it will be repaired by a sprinkler repair company as hired out by Cutting Edge.
To add yourself to the list of irrigation repairs, please send an email to jhoffman@preinnewhof.com and I will pass along your info to Cutting Edge. Please also consider adding flags to the areas where your heads are broken as well to help Cutting Edge with repair.
Let us know if you have any questions.
Progress Report:
Cutting Edge has now completed installation of new storm sewer, catch basins, and manholes throughout the neighborhood.
Upcoming Work:
Cutting Edge will begin the process of restoration throughout the neighborhood. This includes pouring new concrete driveways for the properties where driveways were damaged during construction, placement of new topsoil and restoring yards, and repairing sprinklers that were damaged.
Preparations for road paving are also taking place. This involves grading the road to ensure that the water drains properly off the pavement and into the catch basins. Paving is anticipated to take place in early to mid-September.
Notes:
For those who have, or will be receiving a new concrete driveway apron, the concrete contractor has advised that vehicles should not drive on the surface for four days to allow the concrete to properly cure.
Progress Report:
Cutting Edge has now completed the installation of new storm sewer and structures on Sleepy Hollow Lane.
Upcoming Work:
Some remaining storm sewer will be installed east of Sleepy Hollow Lane near the mailbox area, as well as to the west on Tarry Town Road, which is anticipated to be completed early this week. Once storm sewer installation is complete, Cutting Edge will begin the process of grading the road in preparation for paving.
Notes:
Portions of driveways that needed to be removed during construction will likely be replaced in the near future.
Again, thank you for your patience during this project.
Progress Report:
Cutting Edge completed installation of the Arcadia Water Quality Unit on Thursday at the north end of Sleepy Hollow Lane. Installation of new 8″ sewer for sump pumps to drain into on the portion of Sleepy Hollow Lane north of Tarry Town Drive was also completed.
Upcoming Work:
Cutting Edge will continue the installation of storm sewer on Sleepy Hollow Lane south of Tarry Town Drive.
Progress Report:
This week, Cutting Edge finished laying new storm sewer through the easement and began installing new sewer south to the Tarry Town Road intersection. A new run of sewer was also installed on Sleepy Hollow Lane to the north of the drainage easement to allow for the homes to discharge their sump pumps into.
Upcoming Work:
Next week Tuesday, Cutting Edge will begin placing the large water quality manhole at the north end of Sleepy Hollow Lane. The contractor hopes they can get the manhole installed in one day, but to be safe, plan on two days of traffic being unable to navigate through the north end of the neighborhood.
Once the process of placing the water quality manhole is complete, Cutting Edge will resume storm sewer installation in the Tarry Town Road intersection.
Updated Schedule: Cutting Edge now plans on installing the large water quality manhole at the north end of Sleepy Hollow Lane on this upcoming Tuesday (August 4), not August 10 as previously stated. The contractor hopes they can get the manhole installed in one day, but to be safe, plan on two days of traffic being unable to navigate through the north end of the neighborhood.
Progress Report:
Cutting Edge has completed the installation of new storm sewer and structures on from the north end of Sand Hollow Drive to the Sand Hollow Drive cul-de-sac, and west through the drainage easement to connect to Sleepy Hollow Lane.
Upcoming Work:
The contractor will begin to work north on Sleepy Hollow Lane installing new road underdrain and a dedicated sewer for sump pumps to discharge into, starting where they left off at the west end of the drainage easement.
The new tentative date for installing the large water quality manhole at the north end of Sleepy Hollow Lane is Monday, August 10. The process of installing this manhole will likely completely block traffic through the north end of the neighborhood, so please continue to drive carefully around the job site or park your vehicle at another location and walk to your house if you are comfortable doing so.
Thank you for your continued patience during this project.