May 29, 2026
- Force main yard piping tie-ins are complete.
- All CDF/fairlife flow has been redirected away from Coopersville and is being pumped through the new force main.
- The access drives are paved. Site grading will be completed next week, with irrigation and landscaping to follow shortly after.
- Punch list work will be ongoing for the next several weeks.