- Punch list work is nearly complete, with the exception of the two High-Flow Pump drives that need to be replaced. We are still awaiting dates from Eaton.
- We are working on reviewing O&M manuals and finalizing record plans.
West Randall Lift Station: Construct a second lift station adjacent to the existing West Randall Lift Station to accommodate proposed flows for the Southeast Regional Force Main.
Prein&Newhof
Will Thies, PE
(616) 364-8491
wthies@preinnewhof.com
Contractor
Grand River Construction
(616) 669-5611
Muskegon County
(231) 724-3440
Work completed/in progress:
Anticipated work activities for the coming week:
Work completed/in progress:
Anticipated work activities for the coming week:
Work completed/in progress:
Anticipated work activities for the coming week:
Work completed/in progress:
Anticipated work activities for the coming week: