June 5, 2026
Progress Report:
This week Kentwood continued to install new water main along West River Drive. Water main has been installed through the St. Lawrence intersection and continues east towards Karcher. Kentwood and the Plainfield Water Department began filling and pressure testing the first section of new water main. Marksman, Kentwood’s bore & jack subcontractor, began moving equipment onto the site at the Jupiter Avenue crossing.
Upcoming Work:
Next week, Kentwood will continue to install new water main east towards Jupiter. Kentwood and the Plainfield Water Department will begin the process of disinfecting the first section of new water main. Marksman will set up and complete the trenchless casing installation via bore & jack under Jupiter Avenue.