Georgetown Charter Township - 48th Ave Transmission Main Phase 1

Project Information

Georgetown Charter Township will be constructing a new 24-inch water transmission main on 48th Ave from 200 feet south of Barry Street to Port Sheldon Street. As part of construction, the road will be replaced, as well as driveway approaches on the east side of the road and some storm sewer. The project is anticipated to occur in five stages starting in August of 2024 and working north through October of 2024 and beginning again from May of 2025 to August of 2025. Roads will be closed to through traffic but will remain open to residents.

Access/Traffic:

Traffic detours during the Fall work will be in the following Stages:

Stage 1: Beginning in late August, 48th Ave will be closed from south of Barry Street to south of Van Buren Street. The proposed detour route will route traffic to Chicago Dr, 40th Ave, and Van Buren Street Van Buren Street will remain open temporarily to provide access to 48th Ave north of Van Buren Street. (Map)

Stage 2: In mid-September, the intersection of 48th Ave and Van Buren Street will be closed. The main detour will utilize Port Sheldon St, 40th Ave, and Chicago Drive.  (Map)

Stage 3: In late September, 48th Ave will be closed from north of Van Buren Street to the south drive of Unity CHS. The proposed detour routes traffic to Port Sheldon Street, 40th Ave, and Van Buren Street. This stage will include a temporary closure of UCHS’s south drive. In late October, 48th Ave will be reopened as construction finishes for the year. (Map)

Stage 4: Beginning in late May 2025, 48th Ave will be closed from the north drive of Unity to South of Port Sheldon Street. The proposed detour will utilize Van Buren St, 40th Ave, and Port Sheldon Street. (Map)

Stage 5: In midsummer, the intersection at 48th Ave and Port Sheldon will be closed. The proposed detour routes will utilize Van Buren Street, 36th Ave, Baldwin Street, and 56th Ave. (Map)

Contact

P&N Engineer
Lucas Timmer, PE
Project Manager
616-394-0200

P&N Construction Observer
Joel Bylsma, EIT
616-394-0200

Contractor
Dean’s Excavating
Ben Shepard
616-636-5524

Georgetown Charter Township
Joel Hanenburg
616-226-6005

 

Progress Report:

***Port Sheldon Street & 48th Avenue will be CLOSED from Monday, July 7 until Friday, August 15. Please see Detour Map above***

Construction of culverts and various section of storm sewer continued this week, with construction of the 24-inch transmission main resuming and putting the contractor closer to Port Sheldon Street in preparation for the intersection closure beginning next week.

Upcoming Work:

Construction of the 24-inch transmission main will continue next week as the intersection of 48th Ave & Port Sheldon St will be closed. Storm sewer installation, ditch reconstruction, hydrant drive construction, and the restoration of Sheldon Drive and the north UCHS drive will follow.

Extra Notes:

As a reminder, police officers will continue to be present to ensure safe and effective working conditions for the construction crew and will stop drivers from using the intersection of Port Sheldon Street and 48th Avenue for the duration of the closure.

Please also access UCHS from the south (Van Buren Street) as access is prohibited from the north (Port Sheldon Street) due to construction.

***Port Sheldon Street & 48th Avenue will be CLOSED from Monday, July 7 until Friday, August 15. Please see Detour Map above***

Construction of the 24-inch transmission main continued to the north and the Contractor has reached just south of Port Sheldon Street. Tests on the transmission main south of UCHS’ north drive and just south of Sheldon Drive all passed this week. Storm sewer was started at UCHS’ north drive on Friday.

Upcoming Work:

Storm sewer will continue at UCHS’s north drive and at Sheldon Drive next week. Ditch restoration will also begin along with construction of hydrant field drives and culverts for those field drives. The Contractor has indicated they may begin also restoring UCHS’ north drive and Sheldon Drive with concrete curb so that then after the holidays they can start getting the surface prepared for paving.

Extra Notes:

As a reminder, police officers will continue to be present to ensure safe and effective working conditions for the construction crew and stop drivers from using 48th Ave between UCHS and Port Sheldon Street.

Please also access UCHS from the south (Van Buren Street) as access is prohibited from the north (Port Sheldon Street) due to construction.

Progress Report:

Construction of the 24-inch water transmission main continued and the Contractor was able to get through Sheldon Drive yesterday. Testing on the transmission main that was installed last week and part of this week is starting today and will wrap up mid-week next week.

Upcoming Work:

The Contractor plans on continuing 24 inch water transmission main installation north of Sheldon Drive. In addition, once testing has passed, the Contractor hopes near the end of the week to return back to install storm sewer and start restoring both UCHS’ north drive and Sheldon Drive.

Extra Notes:

As a reminder, police officers will continue to be present to ensure safe and effective working conditions for the construction crew and stop drivers from using 48th Ave between UCHS and Port Sheldon Street. While on site, numerous cars were pulled over and ticketed for entering a construction site.

Please also access UCHS from the south (Van Buren Street) as access is prohibited from the north (Port Sheldon Street) due to construction.

Progress Report: Construction of the 24-inch water transmission main started on Monday, June 9. The contractor crossed the Unity Christian High School north drive on Thursday and the drive is still closed as it has not been restored. In addition, the 24-inch storm sewer underneath UCHS’ driveway was removed and still needs to be returned.

Upcoming Work: Next week the Contractor will continue to install 24-inch water transmission main north to Sheldon Drive. It is anticipated that the Contractor may even cross Sheldon Road next week depending on weather.

Extra Notes:

As a reminder, police officers will continue to be present to ensure safe and effective working conditions for the construction crew and stop drivers from using 48th Ave between UCHS and Port Sheldon Street. While on site, numerous cars were pulled over and ticketed for entering a construction site.

Please also access UCHS from the south (Van Buren) as access is prohibited from Port Sheldon due to construction.

Progress Report:

  • Georgetown Charter Township closed down 48th Avenue between the south driveway of Unity Christian High School to Port Sheldon Street on Monday, June 2. The remainder of the week the Contractor was placing traffic control devices and signs, installing the dewatering system, and relocating a well.
  • On Monday, June 9, 2025 the Contractor began installing the transmission main heading north from Unity Christian’s south driveway.

Upcoming Work:

  • The Contractor plans to continue installing 24 inch water transmission main to the north and will likely be crossing Unity Christian High School’s north driveway and shutting down that driveway.

Extra Notes:

  • As a reminder, police officers will continue to be present to ensure safe and effective working conditions for the construction crew and stop drivers from using 48th Ave between UCHS and Port Sheldon Street
  • In addition, to access UCHS, please utilize Van Buren Street and head to UCHS’ south driveway.

Progress Report:

Georgetown Charter Township will be continuing construction of a new 24-inch water transmission main on 48th Ave from north of Unity Christian High School’s (UCHS’s) south drive to the north side of Port Sheldon Street. Traffic detour/closure starting Monday, June 2, 2025 is described below.

Stage 4: Beginning on Monday, June 2, 2025, 48th Ave will be closed from the north of the south drive of Unity to South of Port Sheldon Street. The proposed detour will utilize Van Buren St, 40th Ave, and Port Sheldon Street. UCHS will be accessible from Van Buren Street only.

The Contractor will be dropping off materials (pipe, fittings, etc.), installing a point dewatering system, and setting up traffic control at the beginning of the week. Near the middle/end of the week the Contractor hopes to start installing pipe.

Extra Notes:

As a reminder, police officers will continue to be present to ensure safe and effective working conditions for the construction crew and stop drivers from using 48th Ave between UCHS and Port Sheldon Street.

Georgetown Charter Township will be continuing construction of a new 24-inch water transmission main on 48th Ave from north of Unity Christian High School’s (UCHS’s) south drive to the north side of Port Sheldon Street. Traffic detours during the summer work will be in the following Stages:

Stage 4: Beginning on June 2, 2025, 48th Ave will be closed from the north of the south drive of Unity to South of Port Sheldon Street. The proposed detour will utilize Van Buren St, 40th Ave, and Port Sheldon Street. UCHS will be accessible from Van Buren Street only. Detour Map

Stage 5: In midsummer**, the full intersection at 48th Ave and Port Sheldon will be closed. This will mean no traffic will be able to travel through this intersection from any direction. The proposed detour routes will utilize Van Buren Street, 36th Ave, Baldwin Street, and 56th Ave. and UCHS will be accessible from Van Buren Street only. Detour Map

**Dates and timing are approximate. We will update this site as more information comes in.

Extra Notes:

As a reminder, police officers will continue to be present to ensure safe and effective working conditions for the construction crew and stop drivers from using 48th Ave between UCHS and Port Sheldon Street.

Some additional restoration and punch list work is also anticipated south of Van Buren Street along 48th Avenue. This work is not anticipated to require a closure of 48th Avenue south of Van Buren Street but may involve shoulder closures or flagging.

Progress Report:

The barricades on 48th Avenue are being removed today allowing for through traffic along 48th Avenue. Give ‘Em A Brake Safety will remove all remaining detour signs before Monday, October 28. Thanks to everyone for their patience with construction this fall.

Upcoming Work:

As a reminder, we will continue water transmission main construction after Unity Christian High School is finished with school for the year in late May or early June of 2025. Construction will continue up through Port Sheldon and is scheduled to be completed by mid-August 2025.

Progress Report: The Contractor finished up water main installation on Monday. Restoration occurred on Monday-Wednesday. No work occurred on site on Thursday and Friday as the Contractor waits on test results for the main.

Upcoming Work: Once the test results come back for the transmission main, the Contractor plans then on finishing up restoration in the area. The Contractor is hoping to be complete with work on site for the year and be off site before or by Friday, October 25, in which at that time the detour will be removed (weather and test result dependent).

Progress Report:

The contractor installed water main through UCHS’s south drive and continued to the north towards the ending point. The last water main pipes for the year were laid, and the hydrant and valves will be installed on Monday, October 14 so testing can be done that week. Restoration south of Van Buren Street has been completed as well as most of the restoration south of UCHS’s south drive. UCHS’s south drive is being restored today and possibly tomorrow with a tentative opening on Monday.

Upcoming Work:

The restoration work will continue into next week and will tentatively be completed by Friday, October 18. The last hydrant and valve will also be installed and testing will be completed next week as well.

Extra Notes:

Although the driveway is tentatively planned to be open by Monday, October 14, it is highly advised that traffic will continue to access Unity Christian High School from the north driveway due to construction continuing to occur until October 18 from the south driveway to Van Buren Street. Testing and restoration will be wrapping up that week and it is anticipated that construction will be finished for the year by Friday, October 18 (weather dependent).

As a reminder, police officers will continue to be present to ensure safe and effective working conditions for the construction crew and stop drivers from using 48th Ave between UCHS and Van Buren Street.