Progress Report:
***PORT SHELDON AND 48TH AVENUE WILL BE REOPENED ON FRIDAY, AUGUST 15 IN THE EVENING***
This week the Contractor was busy working on restoration throughout the project area along 48th Avenue and Port Sheldon Street. Concrete curb was poured at Sheldon Drive on Wednesday and pavement markings were added to Port Sheldon Street and 48th Avenue on Thursday and today. Ditch reconstruction also occurred along 48th Avenue and some ditch enclosure with storm sewer south of Port Sheldon Street along 48th Avenue. Topsoil spreading, raking, seeding, and mulch blanket were also added.
Upcoming Work:
Sheldon Drive will be repaved on Monday, August 18 (delayed until Monday due to curing time for the curb). Paving will be occurring right after school has started (weather dependent) and should be open at the end of the day. Additional restoration and punch list work will also occur into next week.
Extra Notes:
Phase 2 of the 48th Avenue Transmission Main project (north of Port Sheldon) is scheduled to begin in early April of 2026. Port Sheldon Street and 48th Avenue will not be closed down again next year. However, closures of 48th Avenue north of Port Sheldon Street and into Baldwin Street, Tyler Street at 48th Avenue, and Baldwin Street at 48th Avenue will be occurring due to the 24 inch water transmission main project, a sanitary sewer project (from Port Sheldon to Rush Creek), a 12 inch water main project on Tyler Street, and an anticipated OCRC roundabout project at 48th Avenue and Baldwin Street. The anticipated completion of all of these projects is mid-November of 2026.




