Search
Close this search box.

Benton Charter Township - Conrail Lift Station & Interceptor Wastewater System Improvements

Important Information

Important Information

Benton Charter Township is constructing a new lift station and interceptor sewer in the area between Pipestone Road, Interstate 94, and Napier Ave. The map showing the project area will be updated as the project progresses. See further description of the project including anticipated traffic impacts below.

If you have any questions or concerns, please contact any of the project representatives listed below.

____________________________________________

Engineer: Prein&Newhof
Contact: Steve Oosting, PE
(616) 364-8491
soosting@preinnewhof.com

Contractor: Selge Construction Co, Inc.
Kyle Silveus
(574) 229-4908
ksilveus@selgeconstruction.com

Benton Charter Township
Public Works Department
Andy Jordan
(269) 925-0616
ajordan@bentonchartertownship-mi.gov

____________________________________________

Access/Traffic Control

Two separate road closures will occur on Pipestone Road between Napier Ave and Mall Drive.

The first Pipestone Road closure will occur near Aldi and is planned for late October 2023. The closure will be limited to a four week duration. Access to businesses and residences on Pipestone Road will remain available from each direction.

The second Pipestone Road closure will occur near the Meijer gas station and is planned for Spring 2024. The closure will also be limited to a four week duration. Access to businesses and residences on Pipestone Road will remain available from each direction.

See the map to the right showing the closure areas in Pipestone Road and the detour route.

____________________________________________

Home Depot & Hampton Inn

Continuous access to the Hampton Inn and Suite hotel and Home Depot will be maintained throughout the project.

Napier Ave Businesses

Access to businesses in the Napier Ave area will not be affected. A portion of the parking lot west of the Super 8 Hotel will be removed and replaced to install sanitary sewer.

Gaines Ave

The intersection of Gaines Ave and Glencoe Drive is anticipated to be closed the last two weeks of July 2024 for sanitary sewer installation. Traffic will be rerouted via a detour.

Aldi

A portion of the Aldi parking lot will be removed to install a new force main, however, access to Aldi will be maintained via the north Pipestone Road entrance and the Orchards Mall entrance. The work in the Aldi parking lot is anticipated to occur the last two weeks of October 2023. The parking lot will be restored upon completion of the force main work.

water mapdetour graphic

Gravity Sewer Construction

Approximately 1,000 feet of 21-inch gravity sewer has been constructed in the field between the Hampton Inn and truck wash. A trenchless method of sewer construction, known as a “bore & jack,” has also begun near the truck wash. The purpose for this bore & jack operation is so sewer construction can occur near the high voltage transmission towers and billboards on site without disturbing them. 21-inch gravity sewer installation and the bore & jack operation will continue through the next couple of weeks.

 

Gravity Sewer Construction

Gravity sewer installation between the new lift station site and Pipestone Road is nearly complete. No work within Pipestone Rd will occur until the spring.

Gravity sewer installation in the field near the Hampton Inn has resumed in the last week. Construction in the field will continue through to the end of the week.

Gravity Sewer Construction

Gravity sewer installation between the new lift station site and the Brookfield Car Dealership has continued over the last two weeks. Approximately 350’ of 36” sewer has been installed. 36” sewer installation will continue through the end of the week.

 

Lift Station

The meter chamber and the valve chamber piping at the lift station have been installed.

Gravity Sewer Construction

Gravity sewer installation between the new lift station site and the Brookfield Car Dealership has been occurring over the last week. Approximately 100’ of 36” sewer was installed. 36” sewer will continue to be installed in the direction of Pipestone Road as the weather allows. No work is planned to occur this week due to inclement weather.

 

Gravity Sewer installation across Ox Creek has been completed! Construction will continue near the Conrail lift station through the end of next week. No construction will occur between Christmas and New Year’s.

Lift Station

The valve chamber at the lift station has been installed and assembling of piping in the valve chamber has begun.

 

Gravity Sewer Construction Near the Hampton Inn

Gravity sewer installation between the new lift station site and Hampton Inn has been completed. The driveway to Hampton Inn has been restored.

Gravity sewer installation across Ox Creek is planned for this week.

 

Pipestone Road

After a short delay, Pipestone Road has been restored and will be open to traffic by the end of the day!

 

Directional Drill Near the Hampton Inn

Force main installation by horizontal directional drill underneath the unnamed road near the Hampton Inn is complete. With this completed, approximately 95% of all the force main on the project has been installed.

 

Gravity Sewer Construction Near the Hampton Inn

Gravity sewer installation between the new lift station site and Hampton Inn is near completion. Once this run of sewer has been completed, construction of 21” gravity sewer in the area between the Hampton Inn and I94 will continue.

Pipestone Road and Force Main Installation

The installation of the forcemain in Pipestone Road has been completed! Pipestone Road is planned to be paved on Tuesday and is planned to be opened to traffic by the weekend.

 

Gravity Sewer Construction Near the Hampton Inn

Approximately 150’ of 21” gravity sewer has been installed near the Hampton Inn. Installation of gravity sewer between the new lift station site and the Hampton Inn will continue through the end of the week.

Progress Update:

Pipestone Road and Force Main Installation

With Pipestone Road now closed, the first segment of force main installation by horizontal directional drilling is complete. This first segment extends from Pipestone Road to the unnamed private road east of Ox Creek. Next up: open trench construction of approximately 200 feet of force main in Pipestone Road and a connection to the existing Pipestone Road sewer with a new discharge manhole. We expect the work in Pipestone will continue for approximately two more weeks.

 

New Lift Station Construction

The new lift station, located near the Hampton Inn, is now under construction. The wet well base, which is approximately 34 feet deep, has been set.  The rest of the structure is expected to be complete by the end of the week. After the wet well is complete, sewer construction will begin progressing from the wet well to the east across the Hamton Inn frontage. This will be done in stages to maintain access to the Hampton Inn.

Progress Update:

Construction on the Conrail Lift Station and Interceptor project has started! Dewatering and clearing of the site near the lift station has begun in preparation for the wet well installation.

 

Up Next:

Installation of the forcemain from Pipestone Road to the unnamed private road east of Ox Creek is scheduled for late next week. This pipe will be installed by horizontal directional drilling, thereby avoiding clearing and disturbance of the wooded wetlands and creek. Installation of the lift station wet well is also scheduled to begin next week.

 

Pipestone Road Traffic Closure:

The first of two Pipestone Road traffic closures is scheduled to begin October 17. Pipestone Road will be closed to through traffic from Napier Ave to Mall Drive, with a detour following Napier Ave, Plaza Drive, and Mall Drive, as illustrated on the map above. Pipestone Road will be fully closed at the work area located near the Aldi grocery store. Residences and businesses north of the work area, including Aldi, will remain accessible from the north. Businesses south of Aldi will remain accessible from the south. This traffic closure is scheduled from October 17 through November 3.