Work Completed this past week (June 30 to July 4)
- C1, completed storm sewer install on 3rd Street up to Red Bud Trl.
- C3, began water service install on Front Street East of Days.
- C3, began water main connection at Front/Red Bud-East
- C3, completed water main testing on Front Street – Oak to Days.
Work planned for this week (July 7 to July 11)
- C1, anticipated road building on 3rd Street to start July 14th.
- C1, continue sanitary sewer install at Red Bud/Dewey heading West.
- C3, continue water service connections on Front between Oak and Red Bud.
- C3, continue water main connections on Front Street/Red Bud.