City of Buchanan - Downtown Reconstruction

Project Information

This project involves sanitary sewer, storm sewer, and water main utility improvements in downtown Buchanan. Funding for the project is through the USDA-Rural Development Fund (everything except Front Street) and MDOT (Front Street).

Construction is scheduled to begin the week of February 24 and anticipated to be completed in Fall 2025.

Access/Traffic:

Access to homes/businesses will change during the project, but it is the contractor’s responsibility to ensure that there is always access to each property during construction. Deep sewer trench work will be required for this project, so access to drives may change daily depending on work being completed. Each property owner will be notified prior to access being changed.

Mail:

Daily Mail/Package deliveries will still be possible during construction and will use same access location as residents. Construction observer (Zac-P&N) will communicate with USPS any changes in access location to each address.

Garbage Pickup:

Trash/recycling services will continue during construction. Construction observer (Zac-P&N) will coordinate with garbage companies on scheduled pickup days each week and ensure access is possible.

Water Service:

During new water service installation, the contractor will need to gain access to each house/building to compete the installation. On average this causes a water shut off of around 2-4 hours per address. During new water main connection there will be a 4-8 hour shutdown per street. These water shut offs will be communicated each property owner at least 48 hours prior to scheduled work.

Photos

February 20, 2024 – Preconstruction (by Prein&Newhof)

July 24, 2024 – Preconstruction (by Prein&Newhof)

February 27, 2025 – Construction (by Prein&Newhof)

March 6, 2025 – Construction by (Prein&Newhof)

March 10-11, 2025 – Construction (by Prein&Newhof)

March 19, 2025 – Construction (by Prein&Newhof)

April 25, 2025 – Construction (by Prein&Newhof)

May 15, 2025 – Construction (by Prein&Newhof)

June 5, 2025 – Construction (by Prein&Newhof)

 

Contact

P&N Engineer
Mike Schwartz
Project Engineer
269-372-1158

P&N Construction Observer
Zac Culbert
269-312-1799

Contractor
Kamminga & Roodvoets (K&R)
(3rd St, Red Bud, Dewey – USDA)
Jake Klapmust
616-949-0800

Kalin Construction (Front Street – MDOT)
Mike Kalin
269-925-2746

City of Buchanan
City Manager
Tony McGhee
269-695-3844

Future Plans

Work Completed this past week (June 2-7)

  • C1, performed water main tie ins on Red Bud, 3rd Street, Short St, and cut/cap on Main Street. All existing water main on Red Bud/Dewey/3rd/Main St. is dead.
  • C1, began installing dewatering and bypass pump/pipes prepping for Red Bud sanitary sewer install (est. 6/9 start).
  • C3, completed 12” HDD of water main pipe on Front and Days.
  • C3, completed 8” HDD of water main pipe on Days.
  • C3, began water main install at Red Bud/Front.
  • C3, completed insert valve install at Oak/Front St. Intersection reopened to traffic on Wed.
  • Front Street Closed (Eastbound lane only) between Liberty and Rynearson for Retaining Wall repair (not part of Infrastructure project).

Work planned for this week (June 9-14)

  • C1, continue sanitary sewer install at Red Bud/3rd Street. Red Bud South of River will not be accessible to thru traffic.
  • C3, continue water main install on Front Street.
  • Construction update website is up and running.

Work Completed this past week (May 27-31)

  • Continued sanitary and storm sewer install on 3rd Street at City Hall.
  • Installed vibration monitoring equipment on Front Street.
  • Dewatering Treatment unit power washed prior to removal.
  • Construction began on Front Street. Closed to traffic from Oak Street to East of Red Bud.
  • Oak Street intersection closed to traffic on Friday (5/30) to Wed (6/4) for water valve install.
  • Street lights removed. Temp street lighting installed.
  • Front Street Closed (Eastbound lane only) between Liberty and Rynearson sfor Retaining Wall repair (not part of Infrastructure project).

Work planned for this week (June 2-7)

  • Continue storm sewer install on 3rd Street at City Hall.
  • Water main tie ins on Red Bud, 3rd Street, Dewey Street planned for Tuesday (6/3) /Wednesday (6/4).
  • Begin sanitary sewer install on Red Bud, South of 3rd Street. Red Bud South of River will not be accessible to thru traffic.
  • Install insert valves at Oak Street/Front Street intersection Tuesday (6/3).
  • Begin water main install at Red Bud/Front Street.

Front St/Oak Street intersection will be closed from Friday (5/30) until Wed (6/4) for water main valve installation. Once work is complete the intersection will reopen to traffic.

Access to Phillip 66 Gas Station will be possible from Red Bud, South of Front Street. See image below. This is access for gas station only. All other downtown traffic is to use local parking areas and proceed to businesses/residences on foot. This access route will change as construction progresses, updated routes will be posted as those occur.

Front Street closure is now in effect Front Oak Street to Red Bud. Pedestrian access is still allowed on Front Street during construction.

Work Completed this past week (May 19-23)

  • Continued sanitary and storm sewer install on 3rd Street at City Hall.
  • Traffic to Red Bud Fitness switch to Skyline Drive. This will remain the route for traffic here until Red Bud is complete.
  • Water main reconnection on 3rd Street in front of Red Bud Fitness and Dewey/Main St-North completed.
  • Installed vibration monitoring equipment on Front Street.
  • PCMS boards updated to “Front Street Closed Starting 5-27-25”
  • Front Street Closed (Eastbound lane only) between Liberty and Rynearson sfor Retaining Wall repair (not part of Infrastructure project).

Work planned for next week (May 27-31)

  • Continue sanitary and storm sewer install on 3rd Street at City Hall.
  • Work to begin on Front Street Tuesday, May 27th, road closure from Front Street to Oak Street will begin.
  • Street Light removals beginning.
  • Removals of road/curb to begin between Front and Days.

Work Completed this past week (May 12-17)

  • Continued sanitary sewer install, crossed McCoy Creek at 3rd Street.
  • Installed large storm sewer treatment unit at City Hall parking lot.
  • Traffic to Red Bud Fitness switch to Skyline Drive. This will remain the route for traffic here until Red Bud is complete.
  • Water main reconnection on 3rd Street in front of Red Bud Fitness  and Dewey/Main St-North planned for Saturday morning (5/17).
  • Front Street Closed (Eastbound lane only) between Liberty and Rynearson for Retaining Wall repair (not part of Infrastructure project).

Work planned for this week (May 19-23)

  • Continue sanitary sewer install on 3rd Street/City Hall parking lot.
  • Work to begin on Front Street Tuesday, May 27.

Access to City Hall and Lehman’s parking lots will be hampered over the next week due to sewer installation. Alternative parking for City Hall will be off 3rd Street behind Lehman’s Farmhouse. See attached photo. Once construction progresses onto Red Bud access to both parking lots will be possible from Skyline Drive.

Buchanan City Hall Parking Lot Closure

Work Completed this past week (May 5-9)

  • Continued sanitary sewer install on 3rd Street.
  • Completed water service install. All houses/businesses transferred over to the new water main.
  • Traffic to Red Bud Fitness switch to Skyline Drive. This will remain the route for traffic here until Red Bud is complete.
  • Front Street Closed (Eastbound lane only) between Liberty and Rynearson for Retaining Wall repair (not part of Infrastructure project).

Work planned for this week (May 12-16)

  • Continue sanitary sewer install on 3rd Street/City Hall.
  • Crossing the creek with sanitary sewer on Tuesday.
  • Install storm sewer treatment unit once sanitary sewer is across the creek.
  • Water main reconnection on 3rd Street in front of Red Bud Fitness planned for Saturday morning (5/17).

Construction will begin Friday (5/9) with milling off 2 inches of road on Terre Coupe. Paving will begin Monday (5/12). Any remaining asphalt placement needed will be done on Tuesday (5/13). Please reach out if you have any questions.

Zac Culbert
269-312-1799

Work Completed this past week (April 28 – May 2)

  • Continued sanitary sewer install on 3rd Street. Roughly 600 feet from Creek.
  • Continued water service install on Dewey, Main St, and 3rd St.
  • Calibration of flume meter complete.
  • Insert valves install on Red Bud and 3rd Street.
  • Traffic to Red Bud Fitness switch to Skyline Drive. This will remain the route for traffic here until Red Bud is complete.
  • Front Street Closed (Eastbound lane only) between Liberty and Rynearson for Retaining Wall repair (not part of Infrastructure project).

Work planned for this week (May 5 – 9)

  • Continue sanitary sewer install on 3rd Street.
  • Continue water service install on Dewey.
  • Water main reconnection on 3rd Street in front of Red Bud Fitness planned for Saturday morning (5/10).