Work Completed this past week (June 2-7)
- C1, performed water main tie ins on Red Bud, 3rd Street, Short St, and cut/cap on Main Street. All existing water main on Red Bud/Dewey/3rd/Main St. is dead.
- C1, began installing dewatering and bypass pump/pipes prepping for Red Bud sanitary sewer install (est. 6/9 start).
- C3, completed 12” HDD of water main pipe on Front and Days.
- C3, completed 8” HDD of water main pipe on Days.
- C3, began water main install at Red Bud/Front.
- C3, completed insert valve install at Oak/Front St. Intersection reopened to traffic on Wed.
- Front Street Closed (Eastbound lane only) between Liberty and Rynearson for Retaining Wall repair (not part of Infrastructure project).
Work planned for this week (June 9-14)
- C1, continue sanitary sewer install at Red Bud/3rd Street. Red Bud South of River will not be accessible to thru traffic.
- C3, continue water main install on Front Street.
- Construction update website is up and running.