September 18, 2023
The focus this week continued to be on placing sanitary sewer main for Phase I on Griswold Street. Additionally, the road has been built back up to aggregate base to allow Lineage to access their shipping docks from the North. The focus next week will continue to be on sanitary sewer outlined in Phase 1 and begin phase 2.
Work Completed Last Week
- The Contractor continued placing sanitary sewer main on Griswold Street for Phase 1.
- The Contractor placed aggregate base in preparation for asphalt halfway into the Lineage shipping entrance.
- The Contractor placed concrete curb infills for Phase 1.
Anticipated Work This Week
- The Contractor will complete preparations for road rebuilding in Phase I.
- The Contractor will begin preparation for Phase 2.