Important Information

Project Area Map

 

The City of Muskegon is replacing sanitary sewer from Sherman Boulevard and Henry Street to Beidler Street and Young Avenue. The gravity sewer will be installed along portions of Henry Street, Pulaski Avenue, Beidler Street, Poliski Street, Hackley Avenue, and various easement locations.

 

____________________________

Contractor: Kamminga & Roodvoets

Jeff Talsma
(616) 949–0800 ext. 130

____________________________

City of Muskegon Department of Public Works

Leo Evans
(231) 724–6920

____________________________

Prein&Newhof will have personnel in the field on behalf of the City.

Matt Hulst, P.E.
Project Manager
(616) 914–0557
mhulst@preinnewhof.com

Tyler DeNooyer, P.E.
Project Engineer & Onsite Contact
(231) 798–0101
tdenooyer@preinnewhof.com

City of Muskegon - Beidler Sewer Replacement

Work Completed This Week

  • 8-inch sanitary sewer installation on Beidler Street south of Hackley Avenue was completed this week.
  • The new 6-inch water main has been tied into the water system in both locations at Hackley Avenue.  All water services on Beidler Street and Poliski Street, south of Hackley Avenue, have been replaced and the old water main has been abandoned.
  • The deep sanitary sewer has been installed to approximately 100 feet south of Hackley Avenue on Poliski Drive.
  • Aggregate base (gravel) has been installed on Beidler Street, Young Avenue, and Hackley Avenue.

 

Anticipated Work Next Week

  • Sanitary laterals will be drilled into the sideyards and backyards of homes on Beidler Street, south of Hackley Avenue.
  • Concrete curb and gutter, sidewalks, and driveways will begin to be installed on Young Avenue and Beidler Street between Hackly Avenue and Young Avenue.  There will be several days at this time where some residents will not have access to their driveways while the concrete is curing.
  • The first course of asphalt pavement on Hackley Avenue is scheduled to be installed on Wednesday, July 8, 2020.
  • Installation of the deep sanitary sewer on Poliski Drive will continue south toward the dead end.

 

Current Road Closures

  • Beidler Street is closed from Hackley Avenue to Young Avenue.
  • Young Avenue is closed near Beidler Street.
  • Hackley Avenue is closed between Beidler Street and Poliski Drive.  Access to Chalet Floral & Events will be maintained off Beidler Street (accessible from Hancock Avenue) and from Hackley Avenue over the weekend.
  • Poliski Drive will be inaccessible from Hackley Avenue over the holiday weekend.  An access road will be maintained from the south end of Poliski Drive.

Current Road Closures

  • Beidler Street is closed from Hackley Avenue to Young Avenue.
  • Hackley Avenue is closed between Beidler Street and Poliski Drive starting Monday, June 22. Access to Chalet Floral & Events will be maintained off Beidler Street (accessible from Hancock Avenue).

 

Work Completed This Week

  • Hackley Avenue was milled on Monday and the 12-inch sanitary sewer has been installed from Beidler Street to Poliski Drive.
  • The storm sewer on Beidler Street between Young Avenue and Hackley Avenue has been reinstalled.
  • The sanitary sewers in the alleys on Beidler Street have all been reconnected to the new sewer, and all water main which was temporarily removed during sewer installation has been replaced.
  • 8-inch sanitary sewer installation on Beidler Street south of Hackley Avenue began today (Friday, June 26).

 

Anticipated Work Next Week

  • 8-inch sanitary sewer installation on Beidler Street south of Hackley Avenue will continue this week.
  • Water services on Beidler Street and Poliski Drive (south of Hackley) are expected to begin Monday after the water main passes bacteria testing.
  • Kamminga & Roodvoets will begin grading the roadway on Beidler Street between Hackley Avenue and Young Avenue starting Monday (June 29).
  • Due to Independence Day, the contractor will finish up work for the week by 3:00 PM on Thursday, July 2

Notice: Hackley Avenue will be closed to traffic between Beidler Street and Poliski Drive starting Monday June 22.  The closure is anticipated to last 3 weeks.

 

Work Completed This Week

  • Asphalt Paving, Inc. (API) paved the top course of asphalt on Crowley Street this week and the road is now open to all traffic.
  • The 12-inch sanitary sewer on Beidler Street has now been installed from the Lift Station at Young Ave. to Hackley Avenue.
  • The 6-inch water main loop has been installed on Beidler Street and Poliski Drive.

 

Anticipated Work Next Week

  • Hackley Avenue will be milled on Monday and sanitary sewer installation on Hackley will begin midweek.
  • 8-inch sanitary sewer installation on Beidler Street south of Hackley Avenue will begin midweek.
  • Water services on Beidler Street and Poliski Drive (south of Hackley) will begin late in the week after the water main has been tested and chlorinated.
  • Kamminga & Roodvoets will begin grading the roadway on Beidler Street between Hackley Avenue and Young Avenue starting Thursday.

 

Current Road Closures

  • Crowley Street is now open to traffic!
  • Beidler Street is closed from Hackley Avenue to Young Avenue.
  • Hackley Avenue is scheduled to be closed between Beidler Street and Poliski Drive starting Monday, June 22.

 

Current Road Closures

  • Crowley Street is closed with a posted detour from Young Avenue to Laketon Avenue and will likely be open to traffic later next week.
  • Beidler Street is closed from Hackley Avenue to Young Avenue.
  • Hackley Avenue is scheduled to be closed between Beidler Street and Poliski Drive starting Monday, June 22.  Approximately 3 weeks of closure on Hackley is anticipated at this time.

 

Work Completed This Week

  • All of the concrete curbs, driveways, and sidewalk were installed on Crowley Street between Laketon Avenue and Young Avenue.
  • The base course of asphalt was paved on Thursday on Crowley, all castings have been raised, and top soil has been spread over the disturbed areas.
  • The 12-inch sanitary sewer on Beidler Street has been installed up to the alley between Hancock Avenue and Wilson Avenue.

 

Anticipated Work Next Week

  • Kamminga & Roodvoets, Inc. plans to continue installing the sanitary sewer on Beidler Street between Wilson Avenue and Hackley Avenue.
  • The top course of asphalt is scheduled to be paved on Crowley Street on Wednesday, June 17.
  • Work will begin on the new 6-inch water main loop on Beidler Street and Poliski Drive, south of Hackley Avenue on Monday, June 15.
 

Work Completed This Week

  • Kamminga & Roodvoets, Inc. prepared and graded the road subbase and placed gravel on Crowley Street form Young Avenue to Laketon Avenue.
  • Kamminga & Roodvoets, Inc. has installed mainline curb and gutter on Crowley Street from Young Avenue to Laketon Avenue.  The curb radii and some additional sidewalk will be completed on Saturday.
  • The 12-inch sanitary sewer has been installed up to the alley between Lyman Avenue and Wilson Avenue on Beidler Street.
  • The 23 foot deep bore and jack under the 48-inch water main on Wilson Avenue was completed this week by RT Boring, Inc.

 

Anticipated Work Next Week

  • Kamminga & Roodvoets, Inc. plans to continue installing the sanitary sewer on Beidler Street between Young Avenue and Hackley Avenue.
  • The goal on Crowley Street is to continue concrete sidewalk and driveway installation early in the week before paving the base course of asphalt toward the end of the week.

 

Current Road Closures

  • Crowley Street is closed with a posted detour from Young Avenue to Laketon Avenue.
  • Beidler Street is closed from Hackley Avenue to Young Avenue.
  • The right lane of Henry Street is closed at Lyman Avenue to allow trucks to back into Lyman Avenue  and Young Avenue to deliver materials.

 

To all residents on Crowley Street: The contractor will be installing concrete curb and gutter on Crowley Street this week.  The concrete will take up to a week to cure before vehicles will be permitted to drive over it.  Curb and gutter will be installed on Crowley St. according to the following schedule: Tuesday, June 2: Windsor Ave. to Laketon Ave. Friday, June 5: Young Ave. to Windsor Ave. At those times, the road will be closed to ALL traffic and residents will not have driveway access for up to a week after installation.  If you live on Crowley Street, please remove any vehicles you may need from your driveway prior to curb and gutter installation. Parking access in front of residences will be maintained after construction hours and overnight. Thank you in advance for your flexibility, new asphalt is in sight!  
Work Completed This Week
  • Kamminga & Roodvoets, Inc. completed the installation of the water services on Crowley Street. The existing water main on Winston Avenue was connected to the new water main on Crowley Street and the existing water main on Crowley Street was removed from service and abandoned using flowable fill.
  • Kamminga & Roodvoets, Inc. will begin grading for roadway construction and placing the aggregate base course on Saturday.
  • Kamminga & Roodvoets, Inc. removed the asphalt surface on Beidler Street from Hackley Avenue to Young Avenue. The existing curb and gutter and concrete driveways were removed. The sidewalk at the intersections was removed in order to construct ADA ramps that meet current standards. Any other sidewalk that requires replacement for the installation of the sewer and laterals was removed.
  • Kamminga & Roodvoets, Inc. completed the first run of sanitary sewer along Beidler Street from Young Avenue to the south. This run of sewer is approximately 24’ deep. The existing sanitary in the alley between Young Avenue and Lyman Avenue will be connected to the new sanitary sewer system on Saturday.
  Anticipated Work Next Week
  • Kamminga & Roodvoets, Inc. plans to continue constructing the roadway on Crowley Street from Young Avenue to Laketon Avenue.
  • Kamminga & Roodvoets, Inc. plans to continue installing the sanitary sewer on Beidler Street between Young Avenue and Hackley Avenue, including the bore and jack installation under a 48-inch water main at Wilson Avenue.
  Current Road Closures
  • Crowley Street is closed with a posted detour from Young Avenue to Laketon Avenue.
  • Young Avenue is closed at Beidler Street.
  • Beidler Street is closed from Hackley Avenue to Young Avenue.
  • The right lane of Henry Street is closed at Young Avenue to allow trucks to back into Young Avenue to deliver materials.
  • The right lane of Laketon Avenue will be closed intermittently at Crowley Street using a flagger to allow for trucks delivering gravel to back into Crowley Street.

Current Road Closures

  • Crowley Street is closed with a posted detour from Young Avenue to Laketon Avenue.
  • Young Avenue is closed at Beidler Street.
  • Beidler Street is closed from Hackley Ave. to Young Ave.
 

Work Completed This Week

  • Kamminga & Roodvoets has been replacing water services on Crowley all week.  Approximately 6 water services will remain to be completed after this week.
  • The first sanitary manhole of the Beidler Sanitary Sewer was installed at Young Avenue and the wastewater flow on Young Avenue was permanently diverted to the new lift station.
 

Anticipated Work Next Week

  • Kamminga & Roodvoets will to complete the remaining water services on Crowley Street.
  • The water main on Crowley will be tied into the 8 inch water main on Windsor Ave.  The work will require a temporary water service disruption for some residents on Windsor between Kinsey and Henry, and on Crowley between Young and Windsor.
  • Beidler Street from Hackley Ave. to Young Ave. is scheduled to be milled on Tuesday, May 26.
  • Sanitary sewer installation will continue on Beidler Street from Young Ave. to Hackley Ave., working from north to south.  The 12-inch sewer will be 20 to 25 feet deep.

Current Road Closures

  • Crowley Street is closed with a posted detour from Young Avenue to Laketon Avenue.
  • Young Avenue is closed at Beidler Street.
  • The park is closed on Beidler Street between Young Avenue and Lyman Avenue.

 

Work Completed This Week

  • The new water mains on Crowley Street have passed bacteria testing and are now tied into the water system.  Water service replacements have begun.
  • Kamminga & Roodvoets, Inc. has installed the majority of the storm sewer catch basin leads on Crowley St.
  • The lift station at Young Avenue was started up successfully on Friday.
  • Asphalt Paving, Inc. paved the base and top course of asphalt on Division Street between Grand Ave. and Washington Ave.  Division Street is opened back up to two-way traffic.

 

Anticipated Work Next Week

  • Kamminga & Roodvoets will be reaching out to homeowners on Crowley Street to schedule water service replacements over the next 1-2 weeks.
  • Wastewater flows at Young Ave. and Beidler Street will be diverted to the lift station.
  • Sanitary sewer installation will begin on Beidler Street from Young Ave. to Hackley Ave., working from north to south.  The 12-inch sewer will be 20 to 25 feet deep.

Work Completed This Week

  • Kamminga & Roodvoets, Inc. has pressure tested the 10” force main and Consumers Energy has installed power to the Young Avenue Lift Station.
  • Kamminga & Roodvoets, Inc. installed and pressure tested the 8-inch water main and hydrants on Crowley St. from Young Ave. to Laketon Ave.

 

Anticipated Work Next Week

  • Kamminga & Roodvoets, Inc. is disinfecting the water main on Crowley St. over the weekend and plans to perform bacteria testing early next week.
  • After the water main passes bacteria testing, the new water main will be tied into the system and water services will be replaced over a two week period.
  • Kamminga & Roodvoets, Inc plans to install seven storm catch basin leads on Crowley St. next week.
  • The lift station may be started up as soon as next week.

 

Current Road Closures

  • Division Street is closed with a posted detour from Grand Avenue to Washington Avenue.
  • Crowley Street is closed with a posted detour from Young Avenue to Laketon Avenue.
  • Young Avenue is closed at Beidler Street.
  • The park is closed on Beidler Street between Young Avenue and Lyman Avenue.