Work completed/in progress: continue restoration and punchlist
Contract No. 1: Construct force main from West Randall lift station in City of Coopersville to Ottawa County line.
Access/Traffic: Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.
Mail: Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to and when they anticipate it will be returned to its original location.
Garbage Pickup: The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage bins to a central location and return them to the end of your driveway by the end of the work day.
Prein&Newhof – Field
Brad Kuiper
(616) 485-0286
bkuiper@preinnewhof.com
Contractor
Milbocker & Sons
(269) 673-2195
Muskegon County
(231) 724-3440
Work completed/in progress: continue restoration and punchlist
**80th Avenue is closed from Cleveland Street north to Wilson Street. Detour is via 56th Avenue/Ravenna Road.***
Work completed/in progress:
Anticipated work activities within the next couple of weeks:
**80th Avenue is closed from Cleveland Street north to Wilson Street. Detour is via 56th Avenue/Ravenna Road. Closure will be in place for several months.***
Work completed/in progress:
Anticipated work activities for the coming week:
**80th Avenue is closed from Cleveland Street north to Wilson Street. Detour is via 56th Avenue/Ravenna Road. Closure will be in place for several months.***
Work completed/in progress:
Anticipated work activities within the next couple of weeks:
**80th Avenue is closed from Cleveland Street north to Wilson Street. Detour is via 56th Avenue/Ravenna Road. Closure will be in place for several months.***
Work completed/in progress:
Anticipated work activities for the coming week:
**80th Avenue is closed from Cleveland Street north to Wilson Street. Detour is via 56th Avenue/Ravenna Road. Closure will be in place for several months.***
Work completed/in progress:
Anticipated work activities for the coming week:
Resume road building from Applegate to the north.

**80th Avenue is closed from Cleveland Street north to Wilson Street. Detour is via 56th Avenue/Ravenna Road. Closure will be in place for several months.***
Work completed/in progress:
Anticipated work activities for the coming week:
**80th Avenue is closed from Cleveland Street north to Wilson Street. Detour is via 56th Avenue/Ravenna Road. Closure will be in place for several months.***
Work completed/in progress:
Anticipated work activities for the coming week:

**80th Avenue is closed from Cleveland Street north to Heights Ravenna Road. Detour is via 56th Avenue/Ravenna Road. Closure will be in place for several months.***
Work completed/in progress:
Anticipated work activities for the coming week:
**80th Avenue is closed from Cleveland Street north to Heights Ravenna Road. Detour is via 56th Avenue/Ravenna Road. Closure will be in place for several months.***
Work completed/in progress:
Anticipated work activities for the coming week:
