Project Information

Contract No. 1: Construct force main from West Randall lift station in City of Coopersville to Ottawa County line.

Access/Traffic: Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail: Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to and when they anticipate it will be returned to its original location.

Garbage Pickup: The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage bins to a central location and return them to the end of your driveway by the end of the work day.

Contact

Prein&Newhof – Field
Brad Kuiper
(616) 485-0286
bkuiper@preinnewhof.com

Contractor
Milbocker & Sons
(269) 673-2195

Muskegon County
(231) 724-3442

Work completed/in progress:

  • 600 feet of pipe installed along Railroad corridor west of 68th Avenue and pipe installed through casing beneath Railroad
  • Continued fusing lengths of HDPE pipeline.

Anticipated work activities for the coming week:

  • Continue fusing lengths of HDPE pipeline.
  • Resume pipe laying on north side of Railroad corridor toward 72nd Avenue.

Work completed/in progress:

  • Hydrostatic pressure test for first segment of pipe passed.
  • 600′ of pipe installed along Railroad corridor west of 68th Avenue
  • Continued fusing lengths of HDPE pipeline.

Anticipated work activities for the coming week:

  • Continue fusing lengths of HDPE pipeline.
  • Resume pipe laying west of 68th Avenue along the Railroad corridor.

Work completed/in progress:

  • Dug and replaced poor joint near 64th Avenue.
  • Continued fusing lengths of HDPE pipeline.
  • Prepared for pressure test.

Anticipated work activities for the coming week:

  • Perform pressure test.
  • Continue fusing lengths of HDPE pipeline.
  • Resume pipe laying west of 68th Avenue along the Railroad corridor.

Work completed/in progress:

  • Installed pipe through casing beneath 68th Avenue.
  • Installing restraint collar and air release structure west of 68th Avenue.
  • Preparing pipe for pressure test.

Anticipated work activities for the coming week:

  • Dig up and replace poor joint near 64th Avenue.
  • Perform pressure test once joint is replaced.
  • Continue fusing lengths of HDPE pipeline.

Work completed/in progress:

  • Completed force main installation along Railroad corridor on north side of Continental property progressing toward 68th Avenue.

Anticipated work activities for the coming week:

  • Cross 68th Avenue and continue force main installation along Railroad corridor.
  • Prepare for first pressure test of force main.
Work completed/in progress:
  • Continued force main installation along Railroad corridor on north side of Continental property progressing toward 68th Avenue.
  • Flowable filled casings beneath the Railroad and adjacent to the electrical substation.
Anticipated work activities for the coming week:
  • Cross 68th Avenue and continue force main installation along Railroad corridor.
  • Prepare for first pressure test of force main.

Work completed/in progress:

  • No work Mon-Wed due to the winter storm.
  • Plowed work area after winter storm.
  • Continued force main installation along Railroad corridor on north side of Continental property, including pulling the force main through the casing installed adjacent to the electrical substation.

Anticipated work activities for the coming week:

  • Continue force main installation along Railroad corridor on north side of Continental property progressing toward 68th Avenue.

Work completed/in progress:

  • Laid approximately 900′ of force main along Railroad corridor on north side of Continental property.
  • Pulled force main through casing beneath Railroad spur.

Anticipated work activities for the coming week:

  • Continue force main installation along Railroad corridor on north side of Continental property. Install adjacent to electrical substation and continue to 68th Avenue.
  • No work planned for Monday or Tuesday due to cold weather.

Work completed/in progress:

  • Milbocker remobilized from holiday break.
  • Completed destructive sample for cold weather fusion.
  • Began force main installation along Railroad corridor.

Anticipated work activities for the coming week:

  • Continue force main installation along Railroad corridor on north side of Continental property. Cross beneath Railroad spur and install adjacent to electrical substation.

In the coming week, force main installation will begin along the railroad corridor.