Work completed/in progress:
- Milbocker continued fusing HDPE pipe. Approximately 33 fuses have been completed (or 1,700 of force main).
- Milbocker installed the casing beneath the Coopersville and Marne Railway.
Anticipated work activities for the coming week:
- Continue butt-fusing HDPE pipe lengths.
- Begin force main installation at West Randall Lift Station and progress north.