Project Information

Contract No. 2: Construct force main from Ottawa County line to Heights Ravenna Road.

Access/Traffic: Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail: Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to and when they anticipate it will be returned to its original location.

Garbage Pickup: The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage bins to a central location and return them to the end of your driveway by the end of the work day.

Contact

Prein&Newhof – Field
Dave Cadena
(231) 670-7017
dcadena@preinnewhof.com

Contractor
Kamminga & Roodvoets
(616) 949-0800

Muskegon County
(231) 724-3440

powered by Advanced iFrame

Work completed/in progress:

  • Installed shoulder gravel along Moorland from Mt. Garfield to Wilson.
  • Paved HMA top and leveling of Heights Ravenna intersection and opened to traffic.
  • Pavement markings have been completed on Moorland Rd.

Anticipated work activities for the coming week:

  • Continue restoration and punchlist efforts

** Heights Ravenna intersection is anticipated to open November 15**

 

Work completed/in progress:

  • Finished grading pulverized material on Moorland from Mt. Garfield to Wilson
  • Finished paving HMA base and HMA top course on Moorland from Mt. Garfield to Wilson (paving on Moorland is now complete).
  • Paving HMA base course on Heights Ravenna intersection today.

Anticipated work activities for the coming week:

  • Finish paving HMA driveways and the Musketawa trail crossing.
  • Install shoulder gravel along Moorland from Mt. Garfield to Wilson.
  • Anticipate paving HMA leveling and top course on Heights Ravenna intersection tomorrow.

**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. Closure is anticipated to last approximately two more weeks.***

** Heights Ravenna intersection will remain closed until Nov 15th **

 

Work completed/in progress:

  • Hydrostatic test performed and completed.
  • Contract 1/Contract 2 connection made.
  • Contract 2/Contract 3 connection made.

Anticipated work activities for the coming week:

  • Complete Moorland Road and Heights Ravenna Road paving.
  • Continue restoration and punchlist efforts.

**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last as force main construction continues.***

** Heights Ravenna intersection is closed and the closure has been extended to Nov 15th **

Work completed/in progress:

  • Completed force main connection north of Crockery Creek.
  • Force Main is installed from Wilson St to north of Heights Ravenna Rd.
  • HMA base course and top course on Moorland Rd between Heights Ravenna Rd and Mt. Garfield Rd have been paved.
  • Moorland Rd is pulverized from Wilson St to Mt. Garfield Rd.

Anticipated work activities for the coming week:

  • Continue grading and shaping Moorland Rd south of Mt. Garfield Rd.
  • Driveway culvert installation to be continued.
  • Start filling force main for hydrostatic testing.
  • Perform hydrostatic test on force main.

**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last several months as force main construction continues.***

**Ellis Road is open.**

**Heights Ravenna Road will be closed starting 10/20 and will remain closed until top course of paving is complete. Follow posted detour.**

Work completed/in progress:

  • Force main installation along Moorland south of Judson.
  • Curb and gutter placed at Ellis Rd.
  • Paved HMA base and top course on Moorland Rd from Heights Ravenna to Mt. Garfield

Anticipated work activities for the coming week:

  • Continue installation of force main along Moorland Rd.
  • Complete force main connection north of Crockery Creek.
  • Continue crush and shape road work south of Mt. Garfield.
  • Begin installation of shoulder gravel along Moorland Rd starting at Heights Ravenna.
  • Close Heights Ravenna Road and begin force main installation through intersection.
  • Install head walls at the ends of various storm sewer cross culverts.

**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last several months as force main construction continues.***

**ELLIS ROAD IS CLOSED AND WILL REMAIN CLOSED UNTIL TOP COURSE OF PAVING IS COMPLETE. FOLLOW POSTED DETOUR**

 

Work completed/in progress:

  • Completed force main installation along Moorland Rd to 700′ north of Judson Rd.
  • Completed force main connection south of Crockery Creek.
  • Crush and Shape on Moorland Road from Heights Ravenna Rd to Ellis Rd is complete and ready for paving.
  • Concrete Curb and Gutter has been installed at the Hile Rd, Cline Rd and Ellis Rd intersections.
  • Moorland Rd has been pulverized from Ellis Rd to Mt. Garfield Rd.

Anticipated work activities for the coming week:

  • Complete force main connection north of Crockery Creek and pressure test force main north of Crockery Creek.
  • Continue force main installation along Moorland Road south of Crockery Creek.
  • Continue shaping Moorland Rd from Ellis Rd to Mt. Garfield Rd.
  • Pave base and top course on Moorland Rd from Heights Ravenna Rd to Mt. Garfield Rd. Paving is scheduled to begin Monday (10/13)

**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last several months as force main construction continues.***

**ELLIS ROAD TENTATIVELY SCHEDULED TO CLOSE 10/7 THROUGH 10/13 FOR ROAD RECONSTRUCTION. FOLLOW POSTED DETOUR**

 

Work completed/in progress:

  • FORCE MAIN INSTALLATION ACROSS CROCKERY CREEK COMPLETED!
  • Road building underway between Heights Ravenna Road and Ellis Road.
  • Deep road culvert crossings completed. Culvert headwalls under construction.

Anticipated work activities for the coming week:

  • Complete force main connections north and south of Crockery Creek.
  • Pressure test force main north of Crockery Creek.
  • Continue force main installation south of Crockery Creek.
  • Continue road building Moorland Road starting at Heights Ravenna Road and progressing south. First pavement tentatively scheduled for the week of 10/13.

**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last several months as force main construction continues.***

Work completed/in progress:

  • Continued installing force main along Moorland Rd to 200 feet north of Crockery Creek.
  • Started installing retaining walls for deep culverts.

Anticipated work activities for the coming week:

  • Continue installing retaining walls for deep culverts.
  • Force main installation across Crockery Creek.

**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last several months as force main construction continues.***

 

Work completed/in progress:

  • Replaced deep cross culverts on Moorland Rd south of Mt. Garfield Rd and north of Crockery Creek.
  • Force main installation continued along Moorland Rd south of Mt. Garfield Rd.

Anticipated work activities for the coming week:

  • Continue force main installation along Moorland Rd south of Mt. Garfield Rd.

 

**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last several months as force main construction continues.***

Work completed/in progress:

  • Installed force main to 1,500 feet south of Mount Garfield Rd.

Anticipated work activities for the coming week:

  • Replace deep cross culverts on Moorland Rd south of Mount Garfield Rd.
  • Continue installing force main along Moorland Rd.