Important Information

Contract 3: Construct force main from Heights Ravenna Road to Muskegon County Resource Recovery Center.

Access/Traffic: Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail: Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to and when they anticipate it will be returned to its original location.

Garbage Pickup: The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage bins to a central location and return them to the end of your driveway by the end of the work day.

Contact

Prein&Newhof – Field
Brad Kuiper
(616) 485-0286
bkuiper@preinnewhof.com

Contractor
Kamminga & Roodvoets
(616) 949-0800

Muskegon County
(231) 724-3442

Work completed/in progress:

  • K&R off-site for training. Force main installation to resume week of 1/20.

Anticipated work activities for the coming week:

  • Continue force main installation north of Sullivan Rd on MCRRC property.
  • Second pipe crew on-site to begin force main installation south of Apple Avenue on MCRRC property.
  • No work planned for Monday or Tuesday due to cold weather.

Work completed/in progress:

  • Kamminga & Roodvoets remobilized from holiday break.
  • Began force main installation on MCRRC property north of Apple Avenue.

Anticipated work activities for the coming week:

  • K&R off-site for training. Force main installation to resume week of 1/20.

In the coming week, force main installation will begin on MCRRC property.

Work completed/in progress:

  • Preparing site for force main installation including butt-fusion of pipe, topsoil stripping, and dewatering installation.
  • Force main installation has been delayed due to a delay in arrival of force main materials and will not begin until January 6.

Anticipated work activities for the coming week: None.

Work completed/in progress:

  • Preparing site for force main installation including butt-fusion of pipe, topsoil stripping, and dewatering installation.
  • Force main installation has been delayed due to a delay in arrival of force main materials and will not begin until January 6.

Anticipated work activities for the coming week:

  • Continue dewatering installation and pipe fusing.

Work completed/in progress:

  • Preparing site for force main installation including butt-fusion of pipe, topsoil stripping, and dewatering installation.
  • Force main installation has been delayed due to a delay in arrival of force main materials.

Anticipated work activities for the coming week:

  • Begin preparing Ensley Rd extended (south of Apple Avenue) for force main installation.
  • Force main materials expected to arrive this week and force main installation to start the week of December 16.

Work completed/in progress:

  • Completed tree clearing.
  • Butt-fusing HDPE pipe lengths in preparation for pipe laying.
  • Installing dewatering system on MCCRC property north of Apple Avenue.

Anticipated work activities for the coming week:

  • Continue butt-fusing HDPE pipe and dewatering system installation.
  • Start HDPE pipe installation week of December 2.

Work completed/in progress:

  • Completed tree clearing activities and silt fence installation on MCRRC property and Ensley Road.
  • Force main materials continue arriving on-site.

Anticipated work activities for the coming week:

  • Complete tree clearing activities on Price Road and Sherman Boulevard.
  • Continue receiving additional force main materials.
  • Complete butt-fusion training and initial acceptance testing.
  • Install dewatering system on MCRRC property north of Apple Avenue.

Work completed/in progress:

  • Tree clearing activities and silt fence installation on MCRRC property and along Ensley Road.
  • Force main materials beginning to arrive on-site

Anticipated work activities for the coming week:

  • Complete tree clearing activities and silt fence installation.
  • Continue receiving additional force main materials.

Work completed/in progress:

  • Tree clearing activities and silt fence installation on MCRRC property and along Ensley Road.

Anticipated work activities for the coming week:

  • Begin receiving project materials.