Project Information

Contract 3: Construct force main from Heights Ravenna Road to Muskegon County Resource Recovery Center.

Access/Traffic: Local traffic will be maintained during pipeline construction. There may be times when your driveway is inaccessible because pipeline construction is occurring in front of your house or driveway restoration is taking place. The contractor will work with you ahead of time and will make special access arrangements with you if needed.

Mail: Mailboxes that interfere with pipeline construction will be temporarily relocated so that mail service can be maintained during construction. If your mailbox needs to be temporarily relocated, the contractor will inform you of where it has been moved to and when they anticipate it will be returned to its original location.

Garbage Pickup: The contractor will work with you and your waste hauler to maintain service throughout construction. If pipeline construction interferes with your waste haulers ability to pick up your garbage, the contractor will temporarily move your garbage bins to a central location and return them to the end of your driveway by the end of the work day.

Contact

Prein&Newhof – Field
Dave Cadena
(231) 670-7017
dcadena@preinnewhof.com

Contractor
Kamminga & Roodvoets
(616) 949-0800

Muskegon County
(231) 724-3440

powered by Advanced iFrame



Work completed/in progress:

  • Tree clearing activities and silt fence installation on MCRRC property and along Ensley Road.

Anticipated work activities for the coming week:

  • Begin receiving project materials.

Work completed/in progress:

  • Mowing activities completed on MCRRC property. Informational flyers placed along route to help identify potential T&E species (see attached).
  • Resident notification letters sent out to residents along Ensley Road and Apple Avenue regarding upcoming construction work.
  • Tree removals marked along Ensley Road and Apple Avenue.

Anticipated work activities for the coming week:

  • Tree clearing activities and silt fence installation will begin on MCRRC property.

Anticipated work activities for the coming week:

  • Mowing and tree clearing activities will begin on MCRRC property.
  • Tree clearing along Ensley Rd will begin week of October 28.
  • Project has been awarded to Kamminga & Roodvoets of Grand Rapids, Michigan
  • Kamminga & Roodvoets tentatively plans to begin construction in November on Muskegon County property near Apple Avenue