Important Information

This project will include site preparation, removals, and earthwork necessary for the construction of a new park with accompanying sports fields. It will also include supporting facilities such as a restroom building, maintenance building, picnic shelters, large capacity well, electric services & distribution, storm drainage system, irrigation, chips & fines jogging trail w/signage, boardwalk crossings, HMA paving, concrete sidewalks, curb & gutter, flagpole, benches, trash & recycling, trees, dune grass, and turf restoration.

Read more about the Schmidt Heritage Park story on our project page.


 

Engineer:

Prein&Newhof
Kevin Kieft, PE
(231) 798-0101

Prein&Newhof
Matt Levandoski, PLA
(616) 394-0200

Contractor: 

CopperRock Construction
RJ Billmeier
(616) 840-5463


 

Schedule:

Site UtilitiesWinter 2021 – 2022

Site Work Spring 2022 – June 2023

 

Grand Haven Charter Township – Schmidt Heritage Park

Work Completed in July 2022:

  • Crews completed the widening of Ferris Street and the entrance approach concrete work for both Hofma Park and Schmidt Heritage Park.
  • Path work along Ferris Street connecting to Acacia Drive has commenced.
  • Hofma Park parking lot and entrance drive work is underway.
  • Pickleball courts have been poured.
  • Site grading has continued into the softball and baseball fields.  Topsoil has been placed in the soccer fields along the western portion of the site.
  • Irrigation lines have been installed in the soccer field in the Northwest portion of the site.
  • The irrigation well has been installed.
  • Drives and parking areas have aggregate installed.

Site utility work, including water main and sanitary sewer connection to Sweetbriar Road, is complete with paving:


  • A new entrance road has been constructed and gravel placed, along with a portion of the parking areas.
  • Storm sewer and drainage improvements are being completed.
  • Grading and topsoil placement of the NW soccer fields is complete. Irrigation work has begun for these fields.
  • Site work continues on the remaining baseball and softball fields. Pickleball court construction is anticipated in the next few weeks.
  • Ferris Street work will begin the week of July 11th with entrance road construction and is anticipated to be closed for two weeks.

In 2019, Jim Schmidt donated 67 acres of land to Grand Haven Charter Township to be made into a park. Prein&Newhof is working with Grand Haven Charter Township to design, bid, and oversee construction for Phase One of Schmidt Heritage Park.

This phase is planned to have 12 pickleball courts, six soccer fields, a softball field and a baseball field, a trail around the perimeter of the park, restrooms, shelters, and a parking lot. The entrance to the park will be on Ferris Street across from Hofma Park.

Future phases will include two youth baseball diamonds and two softball fields along with more restrooms, shelter, and parking.