Contract #1: Headworks Building Project

Contractor (general): Triangle Construction

Subcontractor (concrete): Van Laan Concrete

Subcontractor (electrical): Windemuller

Subcontractor (mechanical): Allied Mechanical

Subcontractor (earthwork): Jackson–Merkey Contractors

____________________________

Contract #2: Pump Station Improvements

Contractor (general): Grand River Construction

Subcontractor (mechanical): Allied Mechanical

Subcontractor (electrical): Newkirk Electric

Subcontractor (integration): Windemuller

Subcontractor (painting): Dave Cole Decorators

____________________________

Construction is scheduled to last until June 2020.

All work and schedules are weather dependent.

Please contact Prein&Newhof if you have any questions whatsoever regarding construction, the design plans, or if there are any issues. Thank you very much for your patience and cooperation.

Grand Haven Spring Lake Sewer Authority – Wastewater Plant & Pump Station Improvements

Contract 1 Work Completed in May:
  • Began site asphalt paving.
  • Began transitioning old headworks building into storage/garage building.
  • Finalized piping in primary sludge building.
  • Began work on Columbus Avenue reconstruction.

 

Anticipated Work in June:

  • Finish asphalt paving.
  • Finish pipe painting and labeling throughout site.
  • Perform various site restorations, including the installation of a new irrigation system.
  • Complete Columbus Avenue reconstruction.
Contract 1 Work Completed in April:
  • Site stormwater piping
  • Site underdrain piping
  • Demolition of Old Grit Building
  • SE primary clarifier startup
  • Site grading and concrete
  • West startup of primary sludge pump 
  • Site grading and gravel subbase for asphalt

 

Anticipated Work in May:

  • Site concrete and sidewalk
  • Finish pipe painting and labeling throughout site
  • Various site restorations
  • Preparation of base and site asphalt paving
Contract 1 Work Completed in March:
  • Headworks startup and operation with live raw water
  • Grand Haven forcemain and local flows tied into new headworks
  • Completed decommissioning of old headworks
  • SE Primary Clarifier equipment installed
  • Painting in Activated Sludge Building (ASB)
  • East primary sludge pump startup
  • Finalized underground odor control piping for new headworks

 

Anticipated Work in April:

  • SE Primary Clarifier startup
  • West primary sludge pump startup
  • Finish pipe painting and labeling throughout the site
  • Site stormwater and underdrain piping
  • Various site restorations
  • Preparation and grading for sidewalk, site concrete, and paving

Contract 1 work completed since last update (2/4/2020):

  • Piping in the headworks building was painted; grit & screen equipment started up.
  • Tie-in of new headworks to existing 36-inch raw water line
  • Exhaust fans, doors fully installed in Headworks
  • Installation of natural gas line serving the new headworks
  • Demolition of east primary sludge pump and installation of piping
  • Startup of Local Pump Station pumps and VFDs (2/25/2020)
  • Startup of flexible rake bar screen (2/25/2020)
  • Startup of grit washer/compactor (2/25/2020)
  • Activated sludge building work completed

 

Anticipated work in April:

  • Startup of headworks
  • Operation of headworks with live raw water
  • Primary sludge building demolition and equipment installation
  • Southeast primary clarifier equipment installation
  • Painting and finishing in headworks, activated sludge building

 

Contract 1 work completed since last update (1/3/2020):

  • 36-inch raw water line installed
  • Ductwork and exhaust fans in headworks
  • Electrical and lighting work in headworks
  • North activated sludge pumps, valving, and piping


Anticipated work in February:

  • Connection of headworks to raw water line
  • Startup of headworks
  • Completion of activated sludge building
  • Commencement of primary sludge building work
  • Southeast primary clarifier work


Contract 2 work completed since last update (1/3/2020):

SPRING LAKE PUMP STATION:

  • Completed startup of pump station
  • Completed installation of electrical and controls equipment
  • Completed installation of mechanical equipment
  • Completed replacement of roofing material and equipment
  • Began painting walls, floors, ceiling, and equipment


Anticipated work in February:

  • Complete punch list work at both pump stations
  • Begin restoration at Spring Lake Pump Station
  • Complete all restoration in Spring 2020

Contract #1 work completed since last update (12/3/2019):

  • Startup of new south activated sludge pumps
  • Several runs of yard piping
  • Painting in headworks building
  • Overhead door installed in headworks building

 

Anticipated work in January:

  • Several runs of yard piping
  • Existing grit building bypass and tie-in
  • North activated sludge piping, valving, pump installation

 

Contract #2 work completed since last update (12/3/2019):

SPRING LAKE PUMP STATION:

  • Connected station to existing force main
  • Completed installation of pumps, valves, and piping
  • Started painting equipment
  • Poured new sidewalk
  • Continued installation of electrical and controls equipment

 

Anticipated work in January:

  • Complete punch list work at Grand Haven Pump Station
  • Install all remaining equipment at Spring Lake Pump Station
  • Paint remaining equipment and building interior
  • Perform startup of pump station
  • Begin restoration

Contract #1 work completed since last update (11/1/2019):

  • Concrete sidewalk, pipe bollards, awnings installed on headworks building
  • SE primary clarifier demolition and coating
  • Electrical switch-over to new transformer and automatic transfer switch
  • Metal grating and stairs in headworks building

 

Anticipated work in December:

  • Several runs of yard piping
  • South activated sludge pumps startup
  • Painting, caulking, door installation in headworks building
  • Installation of lighting and electrical equipment in headworks building

 

Contract #2 work completed since last update (11/1/2019):

GRAND HAVEN PUMP STATION:

  • Performed startup of pump station and took bypass pumps out of service

 

SPRING LAKE PUMP STATION:

  • Installed temporary pump station bypass system
  • Demolished existing equipment and began installation of new equipment
  • Excavated to prepare for connection to existing force main
  • Poured concrete bases for new pumps

 

Anticipated work in December:

  • Remove bypass system from Grand Haven Pump Station
  • Connect new piping to existing force main at Spring Lake Pump Station
  • Install all remaining equipment
  • Paint equipment and building interior
  • Perform startup of pump station

Contract #1 work completed since last update (10/2/19):

  • Installed precast roof planks and roof grout layer
  • Finished headworks building masonry
  • Staged screening & grit removal equipment in headworks building
  • Began pump and piping replacement work in activated sludge building
  • Pulled wires through conduit for transformer and ATS

 

Anticipated work in November:

  • Painting & metalwork (stairs, grating, railings, etc.)
  • Site piping continuations
  • Activated sludge building startup of south pumps
  • Electrical switchover (new transformer and ATS active)
  • Equipment installation in grit building

 

Contract #2 work completed since last update (10/2/19):

  • Completed installation of piping and valves
  • Set air compressor and installed compressed air piping to control valves
  • Coated wet well interior with epoxy
  • Installed new exterior electrical equipment
  • Electrical crew installs wiring for new automatic transfer switch, disconnect switch, and transformer

 

Anticipated work in November:

  • Install all remaining equipment at Grand Haven Pump Station
  • Paint remaining equipment and building interior
  • Perform startup of pump station and remove bypass pumps
  • Begin construction at Spring Lake Pump Station

Contract #1 work completed since last update (9/5/19):

  • Process piping progress in valve/meter chamber
  • Headworks building masonry
  • 4-inch effluent water line
  • 20-inch force main
  •  
 

Anticipated work in October:

  • Wrap up headworks building masonry
  • Set precast concrete roof on headworks building
  • Painting & metalwork (stairs, grating, railings, etc.)
    •  
 

Contract #2 work completed since last update (9/5/19):

  • Began installing new electrical equipment
  • Existing piping removed and installation of new piping begun
  • Equipment pads, pump bases, and wet well infill concrete poured
  •  
 

Anticipated work in October:

  • Install new pumps, valves, monorails, and remaining piping, electrical, HVAC, and instrumentation equipment
  • Epoxy coat wet well interior
  • Paint equipment and building interior
  • Perform startup of pump station and remove bypass pumps
  •  

Contract #1 work completed since last update (7/31/19):

  • Headworks floor slab, grit channel walls, dumpster room concrete formed & poured with conduit and wall piping in place.
  • Segments of gravity main installed into local wet well
  • Conduit duct banks outside of Primary Sludge Building completed and cased in concrete
  • Local Pump Station wet well was epoxy coated.

 

Anticipated work in September:

  • Install process piping in valve chamber and meter chamber
  • Masonry walls for headworks building
  • Install site piping: 20-inch forcemain, 36-inch headworks effluent pipe, 4-inch effluent water line, underground odor control pipes
  • Small concrete pours: Sloped floor pours, 605′-10″ slab with odor control penetration, compressor pad, ATS/Transformer pad

 

Contract #2 work completed since project began (8/19/19):

  • Pump station bypass system set up and placed in service
  • Demolition of electrical equipment started
  • Wet well interior cleaned and prepared for epoxy coating