Search
Close this search box.

City of Hart - Dryden; Wood; and Jefferson Reconstruction

Important Information

The City of Hart is investing in this neighborhood by replacing aging water main, sanitary sewer, and roadways. This project will take place on numerous roads:

  • Hart Street from Wood Street to Jefferson Street will have new water main installed, sanitary sewer replaced and a new roadway constructed.
  • Wood Street from State Street to Union Street will have the sanitary sewer replaced and a new roadway constructed.
  • Dryden Street from Wigton Street to Johnson Street will have new water main installed, sanitary sewer replaced, and a new roadway constructed.
  • Jefferson Street will have the water main replaced, sanitary sewer replaced and a new roadway constructed.

 

All water services in the area will be replaced into the homes. In addition, all sidewalk will be replaced.  This project will be completed in phases to limit impacts to residents.


Contact

Prein&Newhof
Matt Hulst, PE
Project Manager
(616) 914-0557

Contractor
Hallack Contracting
(231) 873-5081

Road rebuilding continued on Jefferson street last week bringing the road up to aggregate. Additionally, the sidewalk locations were leveled in preparation for the concrete.  The focus this week will be on installing sidewalk and curb on Jefferson and Dryden north of Jefferson, as well as, driveways on Hart Street.

Work Completed Last Week

  • Installation of storm sewer on Jefferson street, at State Street.
  • Removal of sidewalk on Dryden and Jefferson.
  • Preparations for sidewalk and curb installation.
  • Road rebuilding continued on Jefferson, with aggregate base.

Anticipated Work This Week

  • Sidewalk and curb installation on Jefferson and Dryden, north of Jefferson.
  • Driveway installation on Hart Street.
  • Water main tie-in on Jefferson at State Street

Underground utility work and road rebuilding continued on Jefferson street last week with the installation of storm sewer, as well as, water services.  Storm sewer and road rebuilding will continue this week on Jefferson street, as well as, asphalt removal on Dryden from Wood to Jefferson in preparation for water main installation.

Work Completed Last Week

  • Installation of storm sewer on Jefferson street, west of Dryden.
  • Removal of sidewalk on Dryden and Jefferson.
  • Road reconstruction continued on Hart Street with asphalt base paving.
  • Water services on Jefferson street were completed.
  • Road rebuilding continued on Dryden, north of Jefferson, with aggregate base.

Anticipated Work This Week

  • Road rebuilding on Jefferson, continues with aggregate base.
  • Asphalt removal on Dryden from Wood to Jefferson, in preparation for water main installation
  • Water main tie-in on Jefferson at State Street.
  • Storm sewer installation on Jefferson at State Street.

Underground utility work continued on Jefferson street this week with the installation of sanitary sewer main and laterals, as well as, water services. Additionally, curb and sidewalk were installed on Hart street as road rebuilding continues. Water services will continue next week on Jefferson street and road rebuilding will begin on Dryden from Jefferson Street to Johnson Street.

Work Completed This Week

  • Installation of sanitary sewer on Jefferson street, west of Dryden.
  • Installation of sanitary laterals on Jefferson.
  • Road reconstruction continues on Hart Street with curb and sidewalks.
  • Storm sewer on Dryden.
  • Water services on Jefferson street began

Anticipated Work Next Week

  • Road rebuilding on Dryden, north of Jefferson begins.
  • Asphalt removal on Dryden from Wood to Jefferson
  • Water services on Jefferson Street continue.

Please note:  Dave’s Party Store is accessible from Griswold Street and Wood Street, as well as, State Street and Wood Street.

Underground work continues with the installation of sanitary sewer main and laterals on Dryden from Johnson to Jefferson. Sanitary sewer installation will continue on Jefferson Street from State to Dryden and water services on Jefferson.

Work Completed This Week

  • Installation of sanitary sewer on Dryden street, Johnson to Jefferson.
  • Installation of sanitary laterals on Dryden.
  • Road reconstruction continues on Hart Street.
  • Storm sewer on Jefferson.

Anticipated Work Next Week

  • Installation of sanitary sewer on Jefferson, State to Dryden.
  • Sidewalks and curb on Hart Street.
  • Water services on Jefferson Street.

Please note:  Dave’s Party Store is accessible from Griswold Street and Wood Street, as well as State Street and Wood Street.

Work continues with the installation of water main on Jefferson Street, as well as, water services on Hart Street.  Road reconstruction has also began on Hart Street.  Sanitary sewer installation will begin next week on Dryden north of Jefferson.

Work Completed This Week

  • Installation of water main on Jefferson street.
  • Installation of water services on Hart Street.
  • Water main tie-in at Hart and Jefferson.
  • Road rebuilding has begun on Hart Street.

Anticipated Work Next Week

  • Installation of sanitary sewer on Dryden north of Jefferson Street.
  • Road rebuilding on Hart Street will continue.
  • Water services on Jefferson Street.
Road rebuilding on Hart Street.

Underground pipe work continues with the installation of water main and storm sewer on Hart Street, as well as, sanitary sewer on Jefferson.  Water service installation on Hart will begin next week following the tie in at the Jefferson intersection.  Also next week, water main installation will begin on Jefferson.

Work Completed This Week

  • Installation of water main on Hart street.
  • Installation of sanitary sewer on Jefferson.
  • Installation of storm sewer on Hart.
  • Installation of sewer laterals on Jefferson and Hart

Anticipated Work Next Week

  • Installation of water services on Hart.
  • Installation of water main on Jefferson.

Underground pipe work is officially underway with the installation of sanitary sewer and water main on Hart Street.  Water main installation on Hart will continue next week.  Also next week, sanitary sewer on Jefferson and storm sewer on Hart will begin.

Work Completed This Week

  • Installation of sanitary sewer on Hart street stopping at Wood.
  • Installation of water main began on Hart.

Anticipated Work Next Week

  • Installation of water main will continue on Hart.
  • Installation of sanitary sewer on Jefferson.
  • Installation of storm sewer on Hart.

Work on this project has officially begun as of March 25th. Focus for this first week has been on Hart Street from Wood to Jefferson removing the roadway, sidewalk, and driveways.  Starting Monday, April 1, installation of sanitary sewer on Hart Street will begin.

Work Completed This Week

  • Removal of road on Hart Street and Jefferson Street.
  • Installation of groundwater dewatering system on Hart Street.

Anticipated Work Next Week

  • Installation of sanitary sewer on Hart Street.

Work on this project will be starting up again Monday morning March 25. Focus for the first week will be on Hart Street from Wood to Jefferson and on Jefferson Street from State to Hart. Focus will be on removing the roadway, sidewalk, and drives and installation of sanitary sewer on Hart Street.

 

Anticipated Work Next Week

  • Removal of road on Hart Street and Jefferson Street.
  • Installation of groundwater dewatering system on Hart Street.
  • Installation of sanitary sewer on Hart Street.

During this work Hart Street, Jefferson Street and Dryden Street from Jefferson to Johnson will be closed to through traffic.