City of Hart - Dryden; Wood; and Jefferson Reconstruction

Project Information

The City of Hart is investing in this neighborhood by replacing aging water main, sanitary sewer, and roadways. This project will take place on numerous roads:

  • Hart Street from Wood Street to Jefferson Street will have new water main installed, sanitary sewer replaced and a new roadway constructed.
  • Wood Street from State Street to Union Street will have the sanitary sewer replaced and a new roadway constructed.
  • Dryden Street from Wigton Street to Johnson Street will have new water main installed, sanitary sewer replaced, and a new roadway constructed.
  • Jefferson Street will have the water main replaced, sanitary sewer replaced and a new roadway constructed.

All water services in the area will be replaced into the homes. In addition, all sidewalk will be replaced.  This project will be completed in phases to limit impacts to residents.

Contact

Prein&Newhof
Matt Hulst, PE
Project Manager
(616) 914-0557

Contractor
Hallack Contracting
(231) 873-5081

Work on this project will be starting up again Monday morning March 25. Focus for the first week will be on Hart Street from Wood to Jefferson and on Jefferson Street from State to Hart. Focus will be on removing the roadway, sidewalk, and drives and installation of sanitary sewer on Hart Street.

 

Anticipated Work Next Week

  • Removal of road on Hart Street and Jefferson Street.
  • Installation of groundwater dewatering system on Hart Street.
  • Installation of sanitary sewer on Hart Street.

During this work Hart Street, Jefferson Street and Dryden Street from Jefferson to Johnson will be closed to through traffic.