Holland Charter Township - Lakewood Blvd & 120th Ave Sewer Improvement Project

Project Information

Holland Charter Township will be replacing/upsizing the wastewater trunk sewer from a pump station along Lakewood Blvd near US-31 to the east to 120th Avenue, and north on 120th Avenue to James Street.

The project will include lane closures, road closures/detouring, utility excavation/installation, pavement removals, and restoration activities.

Schedule: April – November, 2026

Access/Traffic:

  • Emergency vehicle access will be maintained.
  • Local resident access will be maintained and coordinated with the contractor.
  • There may be times where access will be limited to your residence/business during construction activities. Contractor to coordinate alternate parking locations may be needed for short periods.

Mail:
Temporary mailbox location may be installed. Contractor will coordinate with residents.

Garbage Pickup:
Contractor may request trash receptacles to be replaced at the road the night before.

Contact

P&N Engineer
Jonathan Nelson, PE, Project Manager
(616) 432-6741

P&N Construction Observer
Jesse Boogaard, Construction Observer
(616) 394-0200

Contractor
Kamminga & Roodvoets, Inc. (K&R)
Adam Khodl, Project Manager
(616) 949-0800

Holland Charter Township
Aaron Nyboer, Director of Public Works
(616) 396-1891

There are currently no construction updates available for this project.