Holland Charter Township will be replacing/upsizing the wastewater trunk sewer from a pump station along Lakewood Blvd near US-31 to the east to 120th Avenue, and north on 120th Avenue to James Street.
The project will include lane closures, road closures/detouring, utility excavation/installation, pavement removals, and restoration activities.
Schedule: April – November, 2026
Access/Traffic:
Mail:
Temporary mailbox location may be installed. Contractor will coordinate with residents.
Garbage Pickup:
Contractor may request trash receptacles to be replaced at the road the night before.
P&N Engineer
Jonathan Nelson, PE, Project Manager
(616) 432-6741
P&N Construction Observer
Jesse Boogaard, Construction Observer
(616) 394-0200
Contractor
Kamminga & Roodvoets, Inc. (K&R)
Adam Khodl, Project Manager
(616) 949-0800
Holland Charter Township
Aaron Nyboer, Director of Public Works
(616) 396-1891