© 2025 Prein&Newhof, All Rights Reserved
The work will involve installing new drinking water mains, valves, hydrants and water service pipes from the street to inside the buildings. It will also involve drainage improvements and new sanitary sewer main from Summit to Broadway in Fifth Street as well as new curb and gutter and asphalt pavement and sidewalk ramps.
Current tentative schedule is to begin in July 2025 and be completed by mid-November 2025.
Primary Project Contact
Dan Sorek, PE, Project Manager
Prein&Newhof
(616) 218-2940 (cell)
dsorek@preinnewhof.com
Field Contact
TBD
Contractor for City
Terra Contracting, Muskegon, MI
Contractor Project Manager
Scott Drier, (231) 206-5654
Onsite Contact and 24-Hour Emergency Number
TBD
© 2025 Prein&Newhof, All Rights Reserved