Unfortunately, we were unable to get the paving contractor back this week to finish the top course of asphalt. It was postponed until next week. There was not a lot of visible progress this week other than a few punchlist items.
Progress Report:
- Nearly all concrete has been placed. Only a few slabs need to be placed yet, and a couple of pieces replaced.
- Topsoil, seed, and mulch have been placed, and many areas have been touched up. The sunny areas dry out quicker than the shady areas, which is why the grass is growing better in the shady areas. Please know, we put down the same mixture everywhere. If you have a sunny area, please water it frequently to get the grass to grow before the weeds.
Upcoming Work:
- Final course of asphalt is scheduled for Tuesday, July 8, 2025 (weather dependent). The roads will be closed to ALL TRAFFIC for a few hours during the paving operations until the pavement cools so that the final surface is clean and smooth so it lasts a long time.
- Complete any outstanding concrete work and replace any bad concrete work
- Permanent street signs
- Final piece of the project will be pavement markings on Sanford north of Summit and on Summit
Please remember that when paving operations are taking place, no traffic is allowed until the new asphalt is cooled which will take a couple of hours. We are looking forward to reopening the road very soon. Thank you for your patience, understanding and cooperation during this massive investment into Muskegon Heights infrastructure.
Please remember that the streets are closed to thru traffic, but they will remain open to residents. For the safety of workers, please avoid driving through the construction sites. No on-street parking is allowed within the construction zone.