September 25, 2023
Work completed/in progress:
- Approximately 800′ of force main installed within Colby Street. Force main installed to just west of Burger King driveway.
Anticipated work activities for the coming week:
- Install valving at intersection of Colby Street and Whitehall Road.
- Continue pipe installation within Colby Street, progressing east toward Whitehall Road.