Important Information

This project includes:

  • Installation of 1.25 miles of force main from Hathaway Lakes neighborhood towards the North Bank Trailhead on 144th Avenue.
  • Installation of approximately 0.45 miles of sanitary sewer from the North Bank Trailhead on 144th Avenue to the sewer in 148th Avenue.
  • Replacement of several sections of the asphalt bike non-motorized pathway.
  • Replacement of disturbed roadway on 148th Avenue.

_____________________________

Prein&Newhof will have personnel in the field on behalf of the Project Owner.

Kevin Kieft, PE
Project Manager
(231) 798–0101

Adam Assink, EIT
On-Site Contact/Construction Observer
(616) 212–7551

_____________________________

Contractor: My-Con Inc. of Hudsonville, MI

Kevin Hager
Project Manager
(269) 506–7789

Cole Grysen
24-Hour Emergency Contact
(616) 848–8753

_____________________________

Erik Erhorn
Crockery Township
Township Supervisor
(616) 502–2167

Pat Staskiewicz
Ottawa County Road Commission
Public Utilities Director
(616) 638–0380

Kyle Botbyl
Spring Lake Township
Public Utilities & Streets Superintendent
(616) 502–2162

Crockery Township & Spring Lake Township & Ottawa County Road Commission – North Bank Trail Sewer & Force Main Project

Progress Report

148th Avenue was repaved last week and is now reopened to through traffic. This week, My-Con will be working on restoration of the pathway and surrounding landscaping between 148th Avenue and 144th Avenue. DeWitt Trenching will be mobilizing to the pathway this week, setting up their drill rigs in various places along the path, and clearing brush. Due to the amount of construction vehicles expected to be traveling the pathway this week, the entire North Bank Trail will be closed to pedestrian traffic.

Progress Report

This week, My-Con completed the underground work in 148th Avenue and brought the road back up to grade. My-Con plans to have 148th Avenue repaved and opened to through traffic at the end of next week.

Underground work continues on the North Bank Trail between 148th Avenue and 144th Avenue. The trail will continue to be closed to pedestrian traffic until work is completed on this segment of trail. Work between 148th and 144th Avenues is anticipated to be completed near the end of September, after which the work area will move east of 144th Avenue.

Project Overview

The Ottawa County Road Commission Public Utilities, along with Spring Lake Township and Crockery Township, are beginning construction on a project to connect the Hathaway Lakes sanitary sewer district into the Grand Haven Spring Lake Sewer Authority’s system, with abandonment of the Crockery Wastewater Treatment Plant.

Work has begun at 148th Avenue and will proceed to the east along the North Bank Trail. Current Trail closures are in place from 144th Avenue to 148th Avenue. 148th Avenue is closed to through traffic at the North Bank Trail with the posted detour using State Road, North Fruitport Road and Cleveland Street. Work in this location is anticipated to be completed in mid-September.