July 11, 2024
Progress Report:
This week Milbocker completed the water main installation along Eldon. The new water main was filled with water and passed a pressure test which confirmed there are no leaks in the pipeline. Milbocker worked with the Plainfield Water Department to disinfect the new main and disinfection sampling will continue through Friday. Milbocker has removed sidewalk and topsoil along Mirarmar, between Eldon and Airway, in preparation for water main installation to continue. Milbocker will also begin digging some pits at water service locations along Eldon in preparation for water service replacement next week.
Upcoming Work:
Pending passing disinfection test results, Milbocker will begin replacing copper water service lines within the public right-of-way along Eldon on Monday. It is anticipated that this work will take 3-4 days to complete. Once completed, Milbocker will continue installing new water main along Miramar, starting at Eldon and working north to Airway.