Progress Report:
Black Creek Excavating began the week by completing SESC (Soil Erosion and Sedimentation Control) installation on Monday morning. The remainder of the week was focused on preparing various areas for the installation of concrete pads for benches, wayfinding signs, and trash receptacles. Crews also began work on the pedestrian bridge north of 52nd Street, removing the existing concrete pavement and installing sock pipe underdrain. On Friday afternoon, several concrete pads for benches and trash receptacles were poured between 44th Street and Tradewinds Drive.
Upcoming Work:
Starting Wednesday, the team plans to pulverize the existing pathway as part of surface reconstruction efforts. Crews will continue preparing concrete areas for wayfinding sign installations and plan to pour additional concrete pads throughout the week as weather and site conditions allow.