Important Information

This project is designed to extend the municipal water system and connect homes that have been affected by PFAS contamination.

You might ask: Why is Plainfield Township coordinating the construction project when I live in Algoma Township? The answer is that Algoma Township does not have a municipal water system, and Plainfield Township is extending its water system further into Algoma Township to supply Algoma residents affected by PFAS contamination. This project is a continuation of last year’s water main construction in the Wellington Ridge neighborhood.

All water services are available for connection. Homeowners must schedule the work directly with the contractor they selected and have their water service installed within sixty (60) days of when it became available. Please contact Jeremy Kamp (contact info below) if you have any questions.

_________________________________

Prein&Newhof will have personnel in the field on behalf of Plainfield Charter Township.

Dave Vriesman
On-site Contact
(616) 634–6733

Kevin Gritters, PE
Project Manager
(616) 432–6701

Jeremy Kamp, PE
Project Engineer
(616) 432–6709

_________________________________

Contractor: Dykema Excavating
Greg Dykema
(616) 862–4890

Plainfield Township – Water System Extension: Elstner Ave. & 11 Mile Rd. & Wolven Ave. (Algoma Township)

Progress Report

As of December 23, ninety-seven (97) houses – 98% of the project area – have connected to the municipal water system. See status map above for reference.
All water services are available for connection. Homeowners must schedule the work directly with the contactor they selected. Please contact Jeremy Kamp (contact info to the left) if you have any questions.

What to Expect

January 2022
  • Private water service installation.

_____________________________________________

Progress Report

As of November 12, ninety-five (95) houses – 96% of the project area – have connected to the municipal water system. See status map above for reference.

All water services are available for connection. Homeowners must schedule the work directly with the contactor they selected and have their water service installed within sixty (60) days of when it became available. Please contact Jeremy Kamp (contact info to the left) if you have any questions.

 

What to Expect/Project Timeline

November
  • Final punch list completion
  • Private water service installation

Progress Report

As of October 29, ninety-two (92) houses – 93% of the project – have connected to the municipal water system. See status map above for reference.

All water services are available for connection. Homeowners must schedule the work directly with the contactor they selected and have their water service installed within sixty (60) days of when it became available. Please contact Jeremy Kamp (contact info to the left) if you have any questions.

 

Important Information

All water services are available for connection. Homeowners must schedule the work directly with the contactor they selected and have their water service installed within sixty (60) days of when it became available. Please contact Jeremy Kamp (contact info to the left) if you have any questions.

 

Project Timeline

November
  • Complete the final punch list items
  • Install private water services

Progress Report

As of October 13, ninety (91) houses – 92% of the project – have connected to the municipal water system. See status map above for reference.

 

What to Expect

October
  • Final punch list completion
  • Private water service installation

 

Important Information

All water services are available for connection. Homeowners must schedule the work directly with the contactor they selected and have their water service installed within sixty (60) days of when it became available. Please contact Jeremy Kamp (contact info left) if you have any questions.

 

Anticipated Project Timeline

October
  • Final punch list completion
  • Private water service installation

Progress Report

As of September 24, ninety (90) houses – 91% of the project – have connected to the municipal water system. See status map above for reference.

 

Progress Report

As of September 10, eighty-nine (89) houses – 90% of the project – have connected to the municipal water system. See status map above for reference.

Dykema Excavators is working diligently to wrap up any loose ends throughout the project. Please let us know if you have any concerns.

 

What to Expect/Project Timeline

September
  • Final punch list completion
  • Private water service installation

 

Important Information

All water services are available for connection. Homeowners must schedule the work directly with the contactor they selected and have their water service installed within sixty (60) days of when it became available. Please contact Jeremy Kamp (contact info below) if you have any questions.

Progress Report

Superior Asphalt (Dykema’s paving subcontractor) is planning to be on site this Monday, September 13, to complete necessary asphalt repairs on the Bent Tree Ridge Drive cul-de-sac.

As of September 3, eighty-seven (87) houses – 88% of the project – have connected to the municipal water system. See status map above for reference.

Dykema Excavators is working diligently to wrap up any loose ends throughout the project. Please let us know if you have any concerns.

 

What to Expect

September
  • Final punch list completion
  • Private water service installation

 

Important Information

All water services are available for connection. Homeowners must schedule the work directly with the contactor they selected and have their water service installed within sixty (60) days of when it became available. Please contact Jeremy Kamp (contact info to the left) if you have any questions.

Progress Report

Superior Asphalt (Dykema’s paving subcontractor) is planning on being on site next Tuesday, September 7, to complete necessary asphalt repairs on Bent Tree Ridge Drive and Hopewell Drive.

As of August 26, seventy-seven (79) houses – 80% of the project – have connected to the municipal water system.

Quotation forms have been received for 98 houses (99% of the project). If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so as soon as possible.

Dykema Excavators is working diligently to wrap up any loose ends throughout the project. Please let us know if you have any concerns.

 

What to Expect

September
  • Final punch list completion.
  • Private water service installation.

 

Important Information

All water services are available for connection. Homeowners must schedule the work directly with the contactor they selected and have their water service installed within sixty (60) days of when it became available. Please contact Jeremy Kamp (contact info in sidebar) if you have any questions.

Progress Report

As of August 25, seventy-seven (77) houses – 78% of the project – have connected to the municipal water system.

Quotation forms have been received for 98 houses (99% of the project). If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so as soon as possible.

Dykema Excavators is working diligently to wrap up any loose ends throughout the project. Please let us know if you have any concerns.

 

What to Expect

September
  • Final punch list completion.
  • Private water service installation.

Progress Report

As of August 16, sixty-six (66) houses – 67% of the project – have connected to the municipal water system.

Quotation forms have been received for 97 houses (98% of the neighborhood). If residents have not yet made arrangements with a contractor to complete the private water service work, they must do so as soon as possible.

Dykema Excavators completed final lawn restoration on 11 Mile Road and Elstner Avenue last week. Dykema will be working to resolve any open items over the next few weeks.

 

What to Expect

August
  • Final project clean up and punch list completion