This project is designed to extend the municipal water system and connect homes that have been affected by PFAS contamination.

You might ask: Why is Plainfield Township coordinating the construction project when I live in Algoma Township? The answer is that Algoma Township does not have a municipal water system, and Plainfield Township is extending its water system further into Algoma Township to supply Algoma residents affected by PFAS contamination. This project is a continuation of last year’s water main construction in the Wellington Ridge neighborhood.

_________________________________

Prein&Newhof will have personnel in the field on behalf of Plainfield Charter Township.

Dave Vriesman
On-site Contact
(616) 634–6733

Kevin Gritters, PE
Project Manager
(616) 432–6701

Jeremy Kamp, PE
Project Engineer
(616) 432–6709

_________________________________

Contractor: Dykema Excavating
Greg Dykema
(616) 862–4890

Plainfield Township – Water System Extension: Elstner Ave. & 11 Mile Rd. & Wolven Ave. (Algoma Township)

_____________________________________________

Progress Report

This week:

  • Dykema completed water service stub installation in the 43 North Neighborhood and will complete water service stub installation along 11 Mile Road tomorrow (Saturday).
  • Dykema continued road reconstruction in Wolven Avenue.
  • Dykema started driveway and sidewalk replacement in the 43 North Neighborhood.

 

Next week:

  • Base course paving for Wolven Avenue and Bent Tree Ridge is scheduled for Tuesday, the 15th. After the road is based, Dykema will work on driveway and lawn restoration and place the top course of asphalt in the coming week.
  • Wolven Avenue will be open to traffic in the next two weeks.
  • Dykema will start water main construction on Elstner Avenue Monday.

Please contact a project representative if you have questions or concerns.

 

What to Expect

June
  • Water main construction along Elstner Avenue.
  • Road reconstruction along Wolven Avenue, Bent Tree Ridge, Stoneridge Drive and Hopewell Drive.
  • Installation of water services on private property. This work will be coordinated between each individual property owner and the contractor you select to install your water service.
 
July
  • Water service stub installation along Elstner Avenue.
 
Long-Term
  • Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021. Dykema is currently ahead of this schedule and on track to complete the project in August.

 

Anticipated Project Timeline

JuneWolven Avenue and Bent Tree Ridge road reconstruction
JuneStoneridge Drive water service installation and restoration
June – July43 North water service installation and restoration
June – July11 Mile Road water service installation and restoration
June – AugustElstner Avenue water main, water service installation, and restoration
Progress Report

This week:

  • Dykema completed water service stub installation on Stoneridge Drive except for one service which requires different equipment due to the length of the service stub. This work is scheduled for next Wednesday.
  • Dykema started water service stub installation in the 43 North neighborhood.
  • Dykema started road reconstruction in Wolven Avenue.
 

Next week:

  • Dykema will finish water service stub installation in the 43 North Neighborhood.
  • Dykema will start water service stub installation on 11 Mile Road.
  • Dykema will start water main construction on Elstner Avenue.
  • Dykema will continue to reconstruct Wolven Avenue and complete restoration.
 

Please contact a project representative if you have questions or concerns.

 

What to Expect

June
  • Water service installation in the 43 North neighborhood and along 11 Mile Road.
  • Water main construction along Elstner Avenue.
  • Road reconstruction along Wolven Avenue.
  • Installation of water services on private property. This work will be coordinated between each individual property owner and the contractor you select to install your water service.
 
Long-Term
  • Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021. Dykema is currently ahead of this schedule and on track to complete the project in August.

 

Important Information

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

 

Anticipated Project Timeline

JuneWolven Avenue and Bent Tree Ridge road reconstruction
JuneStoneridge Drive water service installation and restoration
June – July43 North water service installation and restoration
June – July11 Mile Road water service installation and restoration
June – AugustElstner Avenue water main, water service installation, and restoration

Progress Report

This week:

  • Dykema completed water service stub installation on Wolven Avenue.
  • Dykema continued water service stub installation on Stoneridge Drive.
  • Dykema completed water main installation on 11 Mile Road.

Next week:

  • Dykema will pressure test and disinfect the water main along 11 Mile Road.
  • Dykema will finish water service stub installation on Stoneridge Drive.
  • Dykema will start water service stub installation in the 43 North neighborhood.

 

What to Expect

June
  • Water service installation in the 43 North neighborhood.
  • Pressure test and disinfect newly installed water main along 11 Mile Road.
  • Installation of water services on private property. This work will be coordinated between each individual property owner and the contractor you select to install your water service.
Long Term

Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021. Dykema is currently ahead of this schedule and on track to complete the project in August.

 

Projected Timeline

  • June
    • Wolven Avenue and Bent Tree Ridge road reconstruction
    • Stoneridge Drive water service installation and restoration
  • June – July
    • 43 North water service installation and restoration
  • Late June – early July
    • 11 Mile Road water service installation
  • July – August
    • Elstner Avenue water main and water service installation

Progress Report

This week:

  • Dykema completed water service stub installation on Bent Tree Ridge.
  • Dykema continued water service stub installation on Wolven Avenue.
  • Dykema started water main installation on 11 Mile Road.

Next week:

  • Dykema will continue water main construction on 11 Mile Road.
  • Dykema will continue water service stub installation on Wolven Avenue.
  • Dykema will start water service stub installation on Stoneridge Drive.

 

Please contact a project representative if you have questions or concerns.

 

What to Expect

May

  • Water main construction to begin in 11 Mile Road.
  • Water service installation along Wolven Avenue and Stoneridge Drive.
  • Pressure test and disinfect newly installed water main in the 43 North Neighborhood.
  • Installation of water services on private property. This work will be coordinated between each individual property owner and the contractor you select to install your water service.

Long Term

Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021. Dykema is currently ahead of this schedule and on track to complete the project in August.

 

Projected Timeline

  • May
    • Water service installation on Wolven Avenue south of 43 North entrance
    • Bent Tree Ridge Drive restoration
  • May – June
    • Stoneridge Drive water service installation and restoration
  • May – July
    • 11 Mile Road water main and water service installation
  • June – July
    • 43 North water service installation and restoration
  • July – August
    • Elstner Avenue water main and water service installation

Progress Report

You should have received a letter from Plainfield Charter Township last week with instructions outlining the process you need to follow to have your private water service installed. Please contact Jeremy Kamp if you did not receive a letter or have any questions about this process.

Once your water service stub has been installed, a Prein&Newhof representative will be handing out letters informing you that your water service is ready for connection. If you are not home at the time, look for this letter to be attached to the outside of your mailbox or your front door.

This week:

  • Dykema completed water main installation in the 43 North Neighborhood.
  • Dykema completed water main installation on Wolven Avenue.
  • Dykema installed water service stubs on the south end of Wolven Avenue.

Next week:

  • Dykema will start water main construction on 11 Mile Road. A portion of the northern lane of 11 Mile road will have to be milled off prior to water main construction, this work is scheduled for Tuesday.
  • Dykema will continue water service stub installation on Wolven Avenue.

Please contact a project representative if you have questions or concerns.

 

What to Expect

May

  • Water main construction to begin in 11 Mile Road.
  • Water service installation along Wolven Avenue, Stoneridge Drive, and Bent Tree Ridge.
  • Pressure test and disinfect newly installed water main in the 43 North Neighborhood.

Long Term

  • Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021. Dykema is currently ahead of this schedule and on track to complete the project in August.

 

Projected Timeline

  • May
    • Water service installation on Wolven Avenue south of 43 North entrance
  • May – June
    • Bent Tree Ridge Drive water service installation and restoration
    • Stoneridge Drive water service installation and restoration
  • May – July
    • 11 Mile Road water main and water service installation
  • June – July 
    • 43 North water main and water service installation
  • July – August
    • Elstner Avenue water main and water service installation

Progress Report

You will be receiving a letter from Plainfield Charter Township next week with instructions outlining the process you need to follow to have your private water service installed. Please contact Project Engineer Jeremy Kamp if you have any questions about this.

This week:

  • Dykema continued to install water main on Hopewell Drive.
  • Dykema completed water main installation on Stoneridge Drive.
  • Dykema pressure tested the water main in Wolven Avenue and Bent Tree Ridge to ensure there were no leaks. Dykema also worked with the Plainfield Water Department to disinfect this water main.

Next week:

  • Dykema will complete water main construction in the 43 North Neighborhood.
  • Dykema will continue water main construction on Wolven Avenue up to 11 Mile Road.
  • Dykema will begin to install water services on Wolven Avenue.

 

Please contact a project representative if you have questions or concerns.

 

What to Expect

May

  • Water main construction in the 43 North Neighborhood, easement, and Wolven Avenue south of 11 Mile Road.
  • Water service installation south of 11 Mile Road.

 

Long Term

  • Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021. Dykema is currently ahead of this schedule and on track to complete the project in August.

 

Projected Timeline

  • May
    • Windstone Drive restoration
    • Water service installation on Wolven Avenue south of 43 North entrance
  • May – June
    • Bent Tree Ridge Drive water service installation and restoration
    • Stoneridge Drive water service installation and restoration
  • May – July
    • 43 North water main and water service installation
  • mid-June – July 
    • 11 Mile Road water main and water service installation
  • July – August
    • Elstner Avenue water main and water service installation

Progress Report

This week, Dykema:

  • installed water main on Bent Tree Ridge, Wolven Avenue, Stoneridge Drive, and Hopewell Drive.
  • completed driveway restoration on Windstone Drive.
  • started road restoration on Bent Tree Ridge. Paving on Bent Tree Ridge will not take place until after the water services have been installed, but Dykema intends to get the entire road graveled as soon as possible for access.

Next week, Dykema will:

  • complete water main construction on Stoneridge Drive.
  • continue water main construction on Hopewell Drive.
  • pressure test and disinfect the water main in Wolven Avenue, Bent Tree Ridge, and Stoneridge Drive. Once the testing has passed, water service installation will begin on Wolven Avenue.

 

Please contact a project representative if you have questions or concerns.


What to Expect

  • May
    • Water main construction in 43 North Neighborhood.
    • Water service installation on newly installed main south of 43 North.
  • Long Term
    • As soon as the water main in one area is complete, tested, and ready for water service connections, Plainfield Township will communicate with you to start the process of installing water services on private property.
    • Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021.


Anticipated Project Timeline

  • May
    • Windstone Drive restoration
    • Water service installation on Wolven Avenue, south of 43 North entrance
  • May – June
    • Bent Tree Ridge Drive water service installation and restoration
    • Stoneridge Drive water service installation and restoration
  • May – July
    • 43 North water main and water service installation
  • mid-June – July
    • 11 Mile
  • July – August
    • Elstner Drive

Progress Report

Dykema and Lees Trenching installed water services on Windstone Drive this week.

Information regarding how to connect your house to your new water service will be distributed to residents in early May.

Water main construction continued on Wolven Avenue moving from south to north. Dykema will be up to the 43 North development with water main construction along Wolven Avenue by the end of next week. Water main construction continued on Bent Tree Ridge and will be completed early next week. See progress map above for locations where water main has already been installed.

Next week, water main construction will continue on Wolven Avenue up to 43 North and will also start on Stoneridge Drive.

Please contact a project representative if you have questions or concerns.

 

What to Expect

Late April

  • Water main construction on Wolven Avenue and Stoneridge Drive.

Long Term

  • As soon as the water main in one area is complete, tested, and ready for water service connections, Plainfield Township will communicate with you to start the process of installing water services on private property.

Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021.

 

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

Please share this information with your neighbors who may not have email or access to the internet. Thank you for your patience and we look forward to a successful project in your neighborhood!

Progress Report

Dykema tested and disinfected the water main on Windstone Drive, water service installation will follow in the last week of April.

Information regarding how to connect your house to your new water service when it becomes available will be distributed to residents in early May.

Water main construction continued on Wolven Avenue moving from south to north. Water main construction began on Bent Tree Ridge and will be about halfway finished by the end of this week. See progress map above for locations where water main has already been installed.

Next week, water main construction will continue on Bent Tree Ridge and Wolven Avenue.

Please contact a project representative if you have questions or concerns.

 

What to Expect

Late April

  • Water main construction on Wolven Avenue and Bent Tree Ridge.

Long Term

  • As soon as the water main in one area is complete, tested, and ready for water service connections, Plainfield Township will communicate with you to start the process of installing water services on private property.
  • Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021.

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

 

Projected Timeline

  • April – mid-May
    • Windstone Drive
  • April – mid-June
    • Wolven Avenue; 10 Mile Road to 43 North entrance
  • mid-April – mid-June 
    • Bent Tree Ridge Drive
  • May – June
    • Stoneridge Drive
  • May – July
    • 43 North
  • mid-June – July 
    • 11 Mile Road
  • July – August
    • Elstner Drive

Please share this information with your neighbors who may not have email or access to the internet.

Thank you for your patience and we look forward to a successful project in your neighborhood!

Progress Report

Water main construction was completed in Windstone Drive this week. Next week the water main will be tested and disinfected before water services can be installed.

Water main construction began on Wolven Avenue at 10 Mile Road and will continue to move from south to north next week. See progress map above for locations where water main has already been installed.

Tree clearing continued this week and will be finishing up next week.

Please contact a project representative if you have questions or concerns.

 

What to Expect

Early April

  • Water main construction on Wolven Avenue.

Long Term

  • As soon as the water main in one area is complete, tested, and ready for water service connections, Plainfield Township will communicate with you to start the process of installing water services on private property.
  • Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021.

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

 

Projected Timeline

  • April – mid-May
    • Windstone Drive
  • April – mid-June
    • Wolven Avenue; 10 Mile Road to 43 North entrance
  • mid-April – mid-June 
    • Stoneridge Drive
  • May – June
    • Bent Tree Ridge Drive
  • May – July
    • 43 North
  • mid-June – July 
    • 11 Mile Road
  • July – August
    • Elstner Drive

 

Please share this information with your neighbors who may not have email or access to the internet.

Thank you for your patience and we look forward to a successful project in your neighborhood!