Important Information

This project will replace old utilities that are nearing the end of their useful life, including water main, sanitary sewer, and storm sewer. The entire road will be reconstructed, and sidewalks will be replaced as needed.

_________________________________

Prein&Newhof will have personnel in the field on behalf of Plainfield Charter Township.

Onsite Contact: TBD

Kevin Gritters, PE
Project Manager
(616) 432–6701

Jeremy Kamp, PE
Project Engineer
(616) 432–6709

_________________________________

Contractor: Kamminga & Roodvoets (K&R)
(616) 949-0800

Plainfield Township – Water & Wastewater System Improvements: Northville Drive



This Week:

  • Utility companies were marking the existing underground utilities within the project area.
  • Prein&Newhof survey crews were staking the new utilities.


Please do not remove the flags or stakes in your yard; if they are removed it will only delay the project. We apologize for any inconvenience this may cause.

 

Next Week:

  • Tree clearing will take place first half of next week.
  • The existing asphalt road in Northville, between Lakehurst and Leelanau, will be pulverized end of next week in preparation for water main construction to begin on May 23.


Please contact any project representative if you have questions or concerns.

Current Status/Progress Report

Kamminga & Roodvoets (K&R) is scheduled to be on site in two weeks. The week of May 16 will include removal of trees in the road right-of-way which are necessary to install the water main, as well as removal of the existing asphalt which is necessary for the storm and sanitary sewer installation. K&R will be relocating mailboxes to a central location and setting up to start construction in the utility easement near Lakehurst.

Expect to see construction stakes and colored flags showing up in your yards in the next two weeks. Do not remove any of the flags or stakes, as they are marking existing underground utilities and providing information on where the new utilities are to be installed.

Please contact any project representative below if you have questions or concerns.

 

What to Expect

Middle of May

  • Tree Clearing
  • Commence Construction on Site

Long Term

  • Construction will generally progress as follows
  • Northville from Lakehurst to Leelanau
  • Leelanau from Northville to Manitou
  • Northville from Leelanau to 5 Mile Road

 

Date: May 16Event: Begin tree removal on site
Date: May 16Event: Set up traffic control, pulverize existing roads, and begin sanitary sewer construction within the easement area east of Lakehurst
Date: May – Mid JulyEvent: Water main, sanitary sewer, storm sewer, and road reconstruction of Northville between Lakehurst and Leelanau
Date: July – AugustEvent: Water main, sanitary sewer, storm sewer, and road reconstruction of Leelanau between Northville and Manitou
Date: August – OctoberEvent: Water main, sanitary sewer, storm sewer, and road reconstruction of Northville between Leelanau and 5 Mile Road

Current Status/Progress Report

Kamminga & Roodvoets (K&R) intends to start construction of this project in the middle of May 2022. A tentative project timeline is shown below for reference. Construction will generally progress from southwest (Lakehurst) to northeast (5 Mile Rd).

Once work begins, work will generally be conducted between the hours of 7:00 a.m. and 7:00 p.m. on Monday through Friday, with possible work on Saturdays.

For the safety of all residents and construction crews, we ask that residents stay out of the construction area at all times and be aware of construction equipment moving throughout the project area.

K&R will always maintain access for local traffic and emergency vehicles. There will be short periods of time when utilities are being installed in front of your houses and your driveway will be inaccessible. K&R will work to restore driveways as soon as possible during the day and will ensure that all driveways are accessible by the end of the workday. Generally, the immediate work area will be impassible during work hours. See photo below for what a typical sanitary sewer construction work area looks like. Caution is advised while driving through the project area.

Sewer and water service will be maintained throughout construction. However, temporary water shutdowns will be required to connect new water main to existing water mains and to connect new water services to each home. Plainfield’s Water Department will provide advance notice prior to water main shutdowns. K&R will coordinate with individual homeowners when water services are temporarily disconnected and reconnected to the new service.

Please contact any project representative if you have questions or concerns.

 

What to Expect

Middle of May

  • Tree Clearing (5/10)
  • Commence Construction on Site (5/16)

 

Long Term

  • Construction will generally progress as follows
  • Northville from Lakehurst to Leelanau
  • Leelanau from Northville to Manitou
  • Northville from Leelanau to 5 Mile Road
 
 

Project Timeline

Date: May 10

Event: Begin tree removal on site

Date: May 16

Event: Set up traffic control, pulverize existing roads, and begin sanitary sewer construction within the easement area east of Lakehurst

Date: May – Mid July

Event: Water main, sanitary sewer, storm sewer, and road reconstruction of Northville between Lakehurst and Leelanau

Date: July – August

Event: Water main, sanitary sewer, storm sewer, and road reconstruction of Leelanau between Northville and Manitou

Date: August – October

Event: Water main, sanitary sewer, storm sewer, and road reconstruction of Northville between Leelanau and 5 Mile Road

Progress Update

This project was intended to be completed this year (2021). However, due to the large workload and demand on contractors in West Michigan, Plainfield Township became aware that not many contractors had availability left this year and/or that the project cost could come in significantly higher than planned. As a result, the Township allowed contractors to bid on the project for construction in 2021 and/or 2022. On April 26, 2020, the Plainfield Charter Township Board of Trustees awarded the contract to the low bidder, Kamminga & Roodvoets (K&R) of Grand Rapids, MI. The low bid came in below construction cost estimates, but K&R has indicated that their plan is to complete the construction in 2022.

Please contact a project representative if you have questions or concerns.

 

What to Expect

  • Construction will commence on site in the Spring of 2022.
  • Updates will be posted here weekly once construction starts.

Progress Report

This project is under final design. We plan to advertise the project for bidding in late March and open bids in late April. At that time, contract award will be considered by the Township Board, with construction to commence thereafter.

This project will replace old utilities that are nearing the end of their useful life, including water main, sanitary sewer, and storm sewer. The entire road will be reconstructed, and sidewalks will be replaced as needed. The project area is shown on the map.

For the duration of this construction project, we will provide regular updates that will inform you of what is happening presently and what you can expect to see coming up, including water main construction, traffic control, project safety, access to homes, etc.

Please contact a project representative if you have questions or concerns.

 

What To Expect

  • There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.
  • The contractor will be contacting you to make arrangements for mail delivery and garbage collection. Please let us know if you have any problems with this.

 

Please share this information with your neighbors who may not have email or access to the internet.

Thank you for your patience and we look forward to a successful project in your neighborhood!