April 14, 2025
Progress Report:
- Construction of the north plaza subbase and “paver grate” to support the permeable pavers as well as electrical conduit and uplighting is complete.
- Four of the 6 plaza trees are planted.
Upcoming Work:
- The installation of north plaza aggregate base and permeable pavers.
- Utility work in Bridge Street begins next week. The road will be closed for a short period of time with traffic detoured around the construction.