Progress Report: Crews have completed the sanitary sewer on Day Street between M-66 and 2nd Street and are currently working on road reconstruction and restoration. Crews have completed the water main on Grove/Lake and Hill Street on the east side of town and currently working on road reconstruction and restoration. Crews have begun work on the storm/sanitary and water main on Lincoln between Walnut and Cedar Street.
Upcoming Work: The contractor is planning to complete the bore and jack on the sanitary sewer on Lincoln at M-66 next week. Work will continue on Lincoln between Walnut and Cedar.



