September 26, 2024
The contractor has provided an initial schedule that indicates work at the Wastewater Treatment Plant will take place starting in November of 2024 and continue through portions of the winter as is required by the contract.It is their intent to then start with construction on the local streets starting in April of 2025, and being complete with the project by October of 2025. As those dates near, we will post updates as to when work will be occurring on specific streets. Below is a list of preliminary start dates that the contractor’s schedule outlines:
- Grove, Hill, Sheridan, and Lake Streets – April 14, 2025
- Day, Vine, Walnut and Court Streets – June 2, 2025
- Lincoln Street – August 4, 2025
- West Lift Station – April 14, 2025
- Camburn Lift Station – June 2, 2025