West Randall Lift Station

Important Information

West Randall Lift Station: Construct a second lift station adjacent to the existing West Randall Lift Station to accommodate proposed flows for the Southeast Regional Force Main.

Contact

Prein&Newhof
Will Thies, PE
(616) 364-8491
wthies@preinnewhof.com

Contractor
Grand River Construction
(616) 669-5611

Muskegon County
(231) 724-3442

Work completed/in progress:
  • Second wall pour completed and third wall pour preparations underway.
Anticipated work activities for the coming week:
  • The third wall pour is scheduled for Tuesday.

Work completed/in progress:

  • Preparations for the second wall pour were delayed due to weather. The wall forms and bulkheads have been installed.

Anticipated work activities for the coming week:

  • The second wall pour is now scheduled for Monday.

Work completed/in progress:

  • The first wall pour was completed this week (see photos).
  • Conduit and rebar are installed for the second wall pour.

Anticipated work activities for the coming week:

  • Forms will be stripped and moved to the next wall section. The second wall pour is scheduled for next week Wednesday.

Work completed/in progress:

  • Installation of the remaining wall forms was delayed due to rain and high winds this week.
  • All wall pipes and conduit are now in place and the wall is nearly ready for concrete.

Anticipated work activities for the coming week:

  • The date of the first wall pour is scheduled for next week Wednesday.
  • GRC is moving forward with preparing for the second wall pour in the southeast corner of the structure.

Work completed/in progress:

  • Installation of reinforcing steel and conduit for the first wall pour is nearly complete.

Anticipated work activities for the coming week:

  • Grand River Construction will install the remaining form work, with a pour planned for late next week.

Work completed/in progress:

  • Forms and reinforcing steel are being installed for the first wall pour.
  • Base slab has been backfilled.

Anticipated work activities for the coming week:

  • Installation of steel and construction of bulkheads will continue, with a pour tentatively scheduled as early as Friday.
Work completed/in progress:
  • Base slab pour completed yesterday. Attached are photos of the work effort.
Anticipated work activities for the coming week:
  • Backfill the base slab.
  • Installation of reinforcing steel for the first wall pour.

Work completed/in progress:

  • Grand River Construction has completed installation of the steel reinforcing for the base slab and is finalizing preparations for the concrete pour.

Anticipated work activities for the coming week:

  • The base slab concrete pour is planned for the middle of the week.

 

Work completed/in progress:
  • Excavation for the new lift station structure is complete and mud mat is poured.
  • Steel for the base slab has been delivered to the site.
Anticipated work activities for the coming week:
  • Grand River Construction will begin tying steel reinforcing for the base slab (anticipated to take 1-2 weeks).

Work completed/in progress:

  • Schippers Excavating has nearly completed the excavation for the new lift station structure.

Anticipated work activities for the coming week:

  • Grand River Construction will pour a concrete mud mat in the bottom of the excavation, which will be used as the foundation for the structure’s base slab.
  • A crane will be brought to the site as work begins on the base slab.