Work completed/in progress:
- Continued preparation for wet well lining, and dry well stair installation.
- Block filler applied.
Anticipated work activities for the coming week:
- Continue roof construction, preparation for wet well lining, and dry well stairs installation.
- Install dry well ductwork and conduit.
- Begin painting interior walls