West Randall Lift Station

Project Information

West Randall Lift Station: Construct a second lift station adjacent to the existing West Randall Lift Station to accommodate proposed flows for the Southeast Regional Force Main.

Contact

Prein&Newhof
Will Thies, PE
(616) 364-8491
wthies@preinnewhof.com

Contractor
Grand River Construction
(616) 669-5611

Muskegon County
(231) 724-3440

Work completed/in progress:

  • Preparations for the second wall pour were delayed due to weather. The wall forms and bulkheads have been installed.

Anticipated work activities for the coming week:

  • The second wall pour is now scheduled for Monday.

Work completed/in progress:

  • The first wall pour was completed this week (see photos).
  • Conduit and rebar are installed for the second wall pour.

Anticipated work activities for the coming week:

  • Forms will be stripped and moved to the next wall section. The second wall pour is scheduled for next week Wednesday.

Work completed/in progress:

  • Installation of the remaining wall forms was delayed due to rain and high winds this week.
  • All wall pipes and conduit are now in place and the wall is nearly ready for concrete.

Anticipated work activities for the coming week:

  • The date of the first wall pour is scheduled for next week Wednesday.
  • GRC is moving forward with preparing for the second wall pour in the southeast corner of the structure.

Work completed/in progress:

  • Installation of reinforcing steel and conduit for the first wall pour is nearly complete.

Anticipated work activities for the coming week:

  • Grand River Construction will install the remaining form work, with a pour planned for late next week.

Work completed/in progress:

  • Forms and reinforcing steel are being installed for the first wall pour.
  • Base slab has been backfilled.

Anticipated work activities for the coming week:

  • Installation of steel and construction of bulkheads will continue, with a pour tentatively scheduled as early as Friday.
Work completed/in progress:
  • Base slab pour completed yesterday. Attached are photos of the work effort.
Anticipated work activities for the coming week:
  • Backfill the base slab.
  • Installation of reinforcing steel for the first wall pour.

Work completed/in progress:

  • Grand River Construction has completed installation of the steel reinforcing for the base slab and is finalizing preparations for the concrete pour.

Anticipated work activities for the coming week:

  • The base slab concrete pour is planned for the middle of the week.

 

Work completed/in progress:
  • Excavation for the new lift station structure is complete and mud mat is poured.
  • Steel for the base slab has been delivered to the site.
Anticipated work activities for the coming week:
  • Grand River Construction will begin tying steel reinforcing for the base slab (anticipated to take 1-2 weeks).

Work completed/in progress:

  • Schippers Excavating has nearly completed the excavation for the new lift station structure.

Anticipated work activities for the coming week:

  • Grand River Construction will pour a concrete mud mat in the bottom of the excavation, which will be used as the foundation for the structure’s base slab.
  • A crane will be brought to the site as work begins on the base slab.

Grand Rivers Construction’s sub, Schippers, is mobilizing and prepping for site excavation. Excavation is anticipated to take more than a month.