Work completed/in progress:
- Preparations for the second wall pour were delayed due to weather. The wall forms and bulkheads have been installed.
Anticipated work activities for the coming week:
- The second wall pour is now scheduled for Monday.
West Randall Lift Station: Construct a second lift station adjacent to the existing West Randall Lift Station to accommodate proposed flows for the Southeast Regional Force Main.
Prein&Newhof
Will Thies, PE
(616) 364-8491
wthies@preinnewhof.com
Contractor
Grand River Construction
(616) 669-5611
Muskegon County
(231) 724-3440
Work completed/in progress:
Anticipated work activities for the coming week:
Work completed/in progress:
Anticipated work activities for the coming week:
Work completed/in progress:
Anticipated work activities for the coming week:
Work completed/in progress:
Anticipated work activities for the coming week:
Work completed/in progress:
Anticipated work activities for the coming week:
Work completed/in progress:
Anticipated work activities for the coming week:
Work completed/in progress:
Anticipated work activities for the coming week:
Grand Rivers Construction’s sub, Schippers, is mobilizing and prepping for site excavation. Excavation is anticipated to take more than a month.