This week the water service crews were back onsite, more sewer connections were completed and Wilcox roadway was crushed. Focus is starting to turn to rebuilding Thompson and starting utilities on Wilcox.
Work Completed This Week
- Water services were replaced on Thompson and Walnut.
- Sanitary sewer services were completed on Walnut and Thompson, all sewer work is now complete in this phase.
- Restoration was started on Edgewater however this is only temporary and will be readdressed later.
Anticipated Work
- Water service replacement will continue on Thompson and Walnut.
- Sanitary sewer replacement in the Walnut and Wilcox intersection will begin, this intersection has a lot of utilities criss-crossing each other that needs to be untangled.
- Dewatering systems will be installed on Wilcox in preparation for utility installation.
Please note, topsoil and seed was spread on Edgewater this week. Repairs to irrigation will be coming later and the topsoil will be re-raked and seeded at that time.