TUESDAY, AUGUST 16, 2022
Following last week over 90% of the underground work for phase 1 is completed. Bulk of the work moving forward will consist of reconstructing the
Following last week over 90% of the underground work for phase 1 is completed. Bulk of the work moving forward will consist of reconstructing the
Work last week consisted of grading for pathway and transitioning to the road reconstruction. In the last update, we mentioned upcoming concrete work. Now, the
View larger map Progress Update Sanitary sewer installation on Crystal Ave, Highland Ave, Vashti St has been completed, with the exception of one
View larger map Progress Update With work on Francis Ave, Eastman Ave, and Britain Ave substantially complete, the focus of the project has
Work completed this past week: Sanitary Sewer Main replacement in Lakeview Street was completed Storm Sewer Installation in Lakeview Street was completed Top course of
This Week: K&R completed sanitary sewer lateral replacement in Northville Drive between Lakehurst and Leelanau. K&R continued work on storm sewer replacement in Northville Drive
All water services are ready for connection. If you have not already coordinated with a general contractor to get your free water service installed,
This Week: Montgomery completed the 8-inch water main installation along the court streets in the Cottages on the Rogue Neighborhood. Jewell Avenue and 11
Current Status/Progress Update CL Trucking & Excavating has pushed their start date back one week. Water main construction will begin along Algoma Avenue at
This Week: Wyoming completed water main installation on Rapidfall Drive. Wyoming started water main installation on Rapidfall Court. Wyoming continued water service
© 2022 Prein&Newhof, All Rights Reserved