This Week:
- Schippers continued the 16-inch water main installation on Herrington Avenue.
- Schippers began to fill the new water main along Herrington Avenue in preparation for testing in the coming weeks.
- Herrington Avenue was closed to thru traffic and will stay closed until water main construction is complete.
Next Week:
- Schippers will complete water main construction along Herrington Avenue.
- Schippers will install water main across the Jewell Avenue intersection on Tuesday.
- End of next week Schippers will begin to install water main on 10 Mile Road east from Herrington Avenue.
- Schippers will begin to pressure test sections of new water main to ensure there are no leaks.
- Starting Monday, 6/13, Jewell Avenue will be closed to thru traffic.
- Schippers will begin pressure testing and disinfection testing on the first section of new water main in Herrington Avenue.
Please contact any project representative if you have questions or concerns.