Here is this week’s update on the road construction activity in Whitehall. Thank you very much for your patience during this time of inconvenience on Lakeview Street.
Work completed this past week:
- Removing the pavement in Lakeview north of Lewis Street
- Crews focused on replacement of sanitary sewer with over 300 feet of pipe replaced in Lakeview Street
Anticipated work over the next 2 weeks:
- Completing the sanitary sewer installation on Lakeview
- Completing the storm sewer installation on Lakeview
- Completing the placement of the gravel road base material on Lakeview
- Preparation and grading for new concrete curb and gutter to be installed on Lakeview Street
- **Milling and resurfacing of Hall Street between Sophia and Slocum
- **Milling and resurfacing of Elizabeth between Alice and Slocum