This Week:
- Montgomery continued restoration efforts and general project clean up.
- Milling of the existing road in the Cottages on the Rogue neighborhood was completed in preparation for paving next week as part of the Homeowner’s Association paving project.
Next Week:
- Montgomery will finish restoration work, including the repairs of damaged irrigation systems, and general project clean up.
- Final paving of the Cottages on the Rogue neighborhood and Green Timbers cul-de-sac is scheduled for Tuesday (10/11) weather permitting.