The focus this week was on turf restoration and hydroseeding for Phase I, as well as water main tie-ins, water main services, and sanitary mainline for Phase II. The focus next week will continue to be on placing sanitary sewer main and laterals for Phase II.

 

Work Completed This Week

  • Continue turf restoration and hydroseeding on Phase I.
  • Contractor performed phase II watermain tie-in’s at Washington Ave. Morrall Ave. and at Football stadium.
  • Contractor placed new hydrants for Phase II.
  • Contractor performed water services on Phase II.
  • Contractor began sanitary mainline install on Phase II.
  • Contractor performed hand patching of asphalt at driveways behind walk on Phase I.
  • Contractor began placing sanitary laterals to homes on Phase II.

 

Anticipated Work Next Week

  • Perform Phase II watermain tie-in at Southern Ave. on Thursday.
  • Perform water services on Grand Ave.
  • Continue placing sanitary mainline on Phase II.
  • Continue placing sanitary laterals to homes on Phase II.