Sanitary sewer installation continued and the crews are past the difficult crossings for a while. Work continues to progress south towards Polk Road. Road rebuilding is expected to start in the next week or two.
Work Completed Last Week
- The Contractor continued placing sanitary sewer main on Griswold Street for Phase I.
- Additional roadway was removed to continue working south
Anticipated Work This Week
- The Contractor will continue placing sanitary sewer mainline and sanitary sewer manholes for Phase I.
- Phase I roadway rebuilding may start near the end of the week.