Horizontal Directional Drilling (HDD) of pipe at the east end of Crooked Lake has been completed.
Upcoming Schedule:
- The dredging crew is on-site today. Dredging of the lakes for the filter beds is currently scheduled for October and November.
- Filter building construction will begin with footings and foundation, which is anticipated to start next Thursday.