Water main mainline installation is nearing completion on Center Street and work on West Street will begin next week. Water service installation on Center will begin as well.
Work Completed This Week on Center
- Water main from Apple to McLauglin was connected to the system.
- Water main from McLaughlin to Vine was successfully pressure tested and is currently undergoing disinfection.
- Water main is continuing to be installed south of Vine.
Anticipated Work on Center
- Contractor will continue working south installing water main south of Vine.
- Water service installation between Apple and McLaughlin will begin.
- Final testing and disinfecting of the pipe south of McLaughlin will be ongoing.
Anticipated Work on West
- Roadway drive removal is scheduled for early week.
- Possibly begin installation of water main by the end of the week.