Work on Center Street has now transitioned to water service installation and final connections of the water main while work on West Street is now in full swing.
Work Completed This Week on Center
- Water main installation south of Vine was completed, final testing is ongoing prior to connection to system.
- Water service installation has begun, approximately 43 services were completed.
Work Completed This Week on West
- Roadway removal and topsoil stripping was completed.
- Water main installation started working from Apple to the south.
Anticipated Work on Center
- Contractor will continue testing and connecting completed portions of the water main to allow installation of water services.
- Water service installation will continue.
Anticipated Work on West
- Water main installation will continue.