Work on Center Street has now transitioned to water service installation and final connections of the water main while work on West Street is now in full swing.
Work Completed This Week on Center
- Water main connection at Vine Avenue was completed.
- Water service installation continued with another 20 services being completed.
Work Completed This Week on West
- Water main installation continued and is now installed from Apple Avenue to McLaughlin.
Anticipated Work on Center
- Water service installation will continue, this may be completed by the end of the week.
Anticipated Work on West
- Water main installation will continue south of McLaughlin
- Testing on completed portions of water main will begin.