It has been a while since our last update–a lot has happened since then. Underground utility work east of LeBoeuf is now completed and installation of utilities west of LeBoeuf has begun.
Work Completed Since Last Update
- Completed storm sewer east of LeBoeuf.
- Removed the roadway west of LeBoeuf.
- Installed water main west of LeBoeuf, this is currently being tested prior to connections.
- Began installation of sanitary sewer west of LeBoeuf.
Anticipated Work
- Pending successful testing of the new water main, water service replacement will begin west of LeBoeuf.
- Sanitary sewer replacement west of LeBoeuf will continue.
- Grading of the roadway east of LeBoeuf is anticipated to begin.
- Storm sewer installation west of LeBoeuf may begin by the end of the week.