This Week:
- Force main construction continued along Wolven Avenue.
- The remaining force main was installed along Elstner Avenue. Dean’s will be back after the pipe is pressure tested to install the air release structure at the north end of Elstner Avenue.
- Dean’s installed the air release structure on 11 Mile Road.
- The thunderstorm that came through middle of the week washed away a majority of the seeding Dean’s completed last week along Edgerton Avenue and in the Saddle Ridge neighborhood. Dean’s will work on getting these areas reseeded as necessary in the coming week.
Next Week:
- De Witt Trenching will continue to install force main pipe along Wolven Avenue between Prestonwood Drive and Stoneridge Drive.
- Dean’s pipe crew will not be on site next week.